Lodi Unified School District                                            Lodi Unified School District
          George Lincoln Mosher Elementary School                                 George Lincoln Mosher Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                      Project Cost Summary (2016$) - George Lincoln Mosher Elementary School  Project Cost Summary (2016$) - George Lincoln Mosher Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          01 Modernize & Reconfigure Aging Classrooms      $                 81,000 $                    108,000  09 Physical Education Improvements  $              933,000 $                 1,241,000
            1b Replacement or repair of walls                                      9c PE/Fitness Labs
            1b.1 Replace walls                       960 sf  $               39.50 $              38,000  9c.4 New PE/Fitness Labs                2,112 sf  $             404.00 $            853,000
            1e Replacement or repair of floors                                      9c.5 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000
            1e.1 Replace floors                      960 sf  $               14.40 $              14,000
            1f Replacement or repair of ceilings
            1f.1 Replace ceilings                    960 sf  $               27.00 $              26,000  10 Administration & Staff Support  $              176,000 $                    234,000
            1g Patch & Paint Interior/Exterior                                     10a Expanded, reorganized or relocated administration
            1g.1 Patch & paint interior                   960 sf  $                 3.10 $                 3,000  spaces
                                                                                    10a.3 Reconfigure Administration                   750 sf  $             235.00 $            176,000
          02 Existing Building Systems & Toilets           $              460,000 $                    612,000
            2e Replace aging plumbing, upgrade and/or expand                      11 Library & Student Support Services           $              462,000 $                    614,000
            restroom facilities                                                    11d Learning Center
            2e.3 New Restroom                        750 sf  $             556.00 $            417,000  11d.4 Reconfigure Learning Center                1,950 sf  $             237.00 $            462,000
            2e.4 Sitework & Site Improvements                   750 sf  $               57.00 $              43,000
                                                                                  12 Safety, Security & Campus Control            $              225,000 $                    299,000
          03 Site Utilities                                $                       -  $                             -  12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
            Not included in this Facilities Needs Assessment                       12e Safety locks at classroom doors                     45 ea  $             449.00 $              20,000
                                                                                   12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
                                                                                   12g Marquee Sign                               1 ea  $       10,000.00 $              10,000
          04 Classrooms New Construction                   $           1,929,000 $                 2,566,000  12h Fencing with controlled campus entrances
                                                                                    12h.2 Decorative Metal Fencing & Gates                   165 lf  $             252.00 $              42,000
            4a New Construction - Pre-School, DK & Kindergarten                    12i Fire safety equipment, fire alarms and emergency lighting
                                                                                    12i.1 Fire Alarm System                4,940 sf  $                 5.40 $              27,000
            4a.2 New Pre-School, DK & Kindergarten Building                4,455 sf  $             395.00 $         1,760,000  12i.2 Emergency Lighting                4,940 sf  $                 1.40 $                 7,000
            4a.4 Sitework & Site Improvements                4,455 sf  $               38.00 $            169,000  12j New public address/emergency communication
                                                                                   systems                                4,940 sf  $                 7.60 $              38,000
          05 Maker Spaces & Science Labs                   $           1,048,000 $                 1,394,000
            5a ES Science / Creativity Labs                                       13 District Support Facilities                  $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
            5a.5 Reconfigure ES Science / Creativity Labs Building                 1,280 sf  $             243.00 $            311,000
            5a.6 New ES Science / Creativity Labs Building                 1,540 sf  $             440.00 $            678,000
            5a.7 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000  14 Outdoor Learning Environments & Quads  $                 74,000 $                      98,000
                                                                                   14b Learning Courts
                                                                                    14b.2 New Learning Court                3,200 sf  $               23.00 $              74,000
          06 Electives                                     $                       -  $                             -
            Not included in this Facilities Needs Assessment
                                                                                  15 Exterior Play Spaces, Playfields & Hardcourts  $              786,000 $                 1,045,000
                                                                                   15a Kindergarten Play Yard
          07 Performing Arts Improvements                  $              750,000 $                    998,000  15a.1 New Rubberized Surface Play Area                2,000 sf  $               20.00 $              40,000
            7a Music Lab                                                            15a.3 Shade Structure                 1,200 sf  $               90.00 $            108,000
            7a.4 New Music Lab                    1,540 sf  $             449.00 $            691,000  15a.6 New Hardcourts                7,200 sf  $               11.00 $              79,000
            7a.5 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000  15b PE Play Yard & Hardcourts
                                                                                    15a.1 New Rubberized Surface Play Area                6,000 sf  $               20.00 $            120,000
                                                                                    15b.2 Elementary Play Apparatus                        1 ea  $       63,000.00 $              63,000
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $              173,000 $                    230,000  15b.3 Relocate Elementary Play Apparatus                        1 ea  $       18,000.00 $              18,000
            8d New Lunch Shelters                 2,400 sf  $               72.00 $            173,000  15b.6 New Hardcourts             32,500 sf  $               11.00 $            358,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  509
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District