Page 541 - Facilities Master Plan 2016
P. 541

Lodi Unified School District                                            Lodi Unified School District
          John Muir Elementary School                                             Clyde W. Needham Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - John Muir Elementary School           Project Cost Summary (2016$) - Clyde W. Needham Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          The following items are excluded from this budget:                      01 Modernize & Reconfigure Aging Classrooms     $           2,301,000 $                 3,060,000
           Utility hook-up fees & City connection fees.                            1a Structural Strengthening
           Offsite work and traffic signals.                                        1a.1 Roof/Wall connections                6,984 sf  $               19.30 $            135,000
           Land acquisition costs.                                                  1a.2 Wall strengthening                6,984 sf  $               13.50 $              94,000
           Hazardous material surveys, abatement, and disposal.                    1b Replacement or repair of walls
           Escalation (Costs are in 2016$ calculated to the end of the year).       1b.1 Replace walls                    6,984 sf  $               39.50 $            276,000
                                                                                    1b.2 Repair walls                     7,680 sf  $               12.60 $              97,000
                                                                                   1c Replacement or repair of windows
                                                                                    1c.1 Replace windows               14,664 sf  $               18.00 $            264,000
                                                                                   1d Replacement or repair of doors (other than safety locks
                                                                                   @ classroom doors)
                                                                                    1d.1 Replace doors & hardware             14,664 sf  $               13.50 $            198,000
                                                                                   1e Replacement or repair of floors
                                                                                    1e.1 Replace floors                   6,984 sf  $               14.40 $            101,000
                                                                                    1e.2 Repair floors                    7,680 sf  $               10.80 $              83,000
                                                                                   1f Replacement or repair of ceilings
                                                                                    1f.1 Replace ceilings                 6,984 sf  $               27.00 $            189,000
                                                                                    1f.2 Repair ceilings                  7,680 sf  $                 8.10 $              62,000
                                                                                   1g Patch & Paint Interior/Exterior
                                                                                    1g.1 Patch & paint interior             14,664 sf  $                 3.10 $              45,000
                                                                                   1o Replace Existing Roofing             31,137 sf  $               20.93 $            652,000
                                                                                   1p Repair Existing Covered Walkways / Hallways                8,090 sf  $               13.00 $            105,000
                                                                                  02 Existing Building Systems & Toilets          $           1,220,000 $                 1,623,000
                                                                                   2a HVAC system upgrades             14,664 sf  $               29.00 $            425,000
                                                                                   2b Lighting upgrades - new interior lighting & controls             14,664 sf  $               15.00 $            220,000
                                                                                   2c Electrical upgrades
                                                                                    2c.1 Upgrade electrical wiring & increase electrical
                                                                                    outlets                            14,664 sf  $                 9.00 $            132,000
                                                                                   2d Plumbing system upgrades             14,664 sf  $               11.00 $            161,000
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.2 Reconfigure Existing Restroom                   600 sf  $             222.00 $            133,000
                                                                                    2e.3 Structural Upgrade to Existing Building                   600 sf  $               72.30 $              43,000
                                                                                   2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)             14,664 sf  $                 7.20 $            106,000
                                                                                  03 Site Utilities                               $           1,296,000 $                 1,724,000
                                                                                   (For entire campus and site)
                                                                                   3a New gas service lines           307,305 sf  $                 0.32 $              98,000
                                                                                   3b New sewer service lines           307,305 sf  $                 0.63 $            194,000
                                                                                   3c New water service lines           307,305 sf  $                 0.68 $            207,000
                                                                                   3d New electrical mains and distribution           307,305 sf  $                 1.17 $            360,000
                                                                                   3e New storm drainage system           307,305 sf  $                 0.68 $            207,000
                                                                                   3f Electrical Capacity Upgrades                        1 ls  $     230,000.00 $            230,000



         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  512
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   536   537   538   539   540   541   542   543   544   545   546