Lodi Unified School District                                            Lodi Unified School District
          John Muir Elementary School                                             John Muir Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - John Muir Elementary School              Project Cost Summary (2016$) - John Muir Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            4d Student Collaboration Lab
            4d.1 New Student Collaboration Lab, 1- Story                1,915 sf  $             426.60 $            817,000  12 Safety, Security & Campus Control  $              962,000 $                 1,279,000
            4d.2 Sitework & Site Improvements                   958 sf  $               38.00 $              36,000  12b Safety improvements to and/or new parent/bus drop-off areas and parking
                                                                                    12b.1 New Parking Lot                 5,000 sf  $               16.00 $              80,000
                                                                                    12b.5 New Drop-off Area                7,000 sf  $               18.00 $            126,000
          05 Maker Spaces & Science Labs                   $           1,472,000 $                 1,958,000  12b.10 Slurry Coat & Stripe Existing Paving             19,800 sf  $                 2.00 $              40,000
            5a ES Science / Creativity Labs                                        12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
            5a.6 New ES Science / Creativity Labs Building                 3,080 sf  $             440.00 $         1,355,000  12e Safety locks at classroom doors                     35 ea  $             449.00 $              16,000
            5a.7 Sitework & Site Improvements                3,080 sf  $               38.00 $            117,000  12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
                                                                                   12g Marquee Sign                               1 ea  $       10,000.00 $              10,000
                                                                                   12h Fencing with controlled campus entrances
          06 Electives                                     $                       -  $                             -  12h.2 Decorative Metal Fencing & Gates                   180 lf  $             252.00 $              45,000
            Not included in this Facilities Needs Assessment                       12i Fire safety equipment, fire alarms and emergency lighting
                                                                                    12i.1 Fire Alarm System             35,330 sf  $                 5.40 $            191,000
                                                                                    12i.2 Emergency Lighting             35,330 sf  $                 1.40 $              49,000
          07 Performing Arts Improvements                  $              750,000 $                    998,000  12j New public address/emergency communication
            7a Music Lab                                                           systems                             35,330 sf  $                 7.60 $            269,000
            7a.4 New Music Lab                    1,540 sf  $             449.00 $            691,000  12k Intrusion alarms             35,330 sf  $                 1.80 $              64,000
            7a.5 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000
                                                                                  13 District Support Facilities                  $                       -  $                             -
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $           1,720,000 $                 2,288,000  Not included in this Facilities Needs Assessment
            8a Elementary/Middle School multipurpose rooms
            8a.2 Modernize Multipurpose Room                2,700 sf  $               99.00 $            267,000
            8a.4 New Multipurpose Room                2,250 sf  $             494.00 $         1,112,000  14 Outdoor Learning Environments & Quads  $                 55,000 $                      73,000
            8a.5 Sitework & Site Improvements                2,250 sf  $               38.00 $              86,000  14b Learning Courts
            8c Food service areas                                                   14b.2 New Learning Court                2,400 sf  $               23.00 $              55,000
            8c.2 Modernize Food Service                1,200 sf  $             175.00 $            210,000
            8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $              45,000
                                                                                  15 Exterior Play Spaces, Playfields & Hardcourts  $           1,041,000 $                 1,385,000
                                                                                   15a Kindergarten Play Yard
          09 Physical Education Improvements               $              933,000 $                 1,241,000  15a.1 New Rubberized Surface Play Area                1,200 sf  $               20.00 $              24,000
            9c PE/Fitness Labs                                                      15a.3 Shade Structure                 1,200 sf  $               90.00 $            108,000
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00 $            853,000  15a.7 Slurry Coat & Stripe Existing Hardcourts                7,200 sf  $                 3.00 $              22,000
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000  15b PE Play Yard & Hardcourts
                                                                                    15a.1 New Rubberized Surface Play Area                5,000 sf  $               20.00 $            100,000
                                                                                    15b.2 Elementary Play Apparatus                        1 ea  $       63,000.00 $              63,000
          10 Administration & Staff Support                $              413,000 $                    549,000  15b.4 Shade Structure                2,400 sf  $               90.00 $            216,000
            10a Expanded, reorganized or relocated administration                   15b.6 New Hardcourts               14,400 sf  $               11.00 $            158,000
            spaces                                                                  15b.7 Slurry Coat & Stripe Existing Hardcourts             28,600 sf  $                 3.00 $              86,000
            10a.2 Modernize Administration                2,000 sf  $             118.00 $            236,000  15c Playfields
            10b Staff Collaboration/Work Rooms                                      15c.1 Repair Playfields             87,900 sf  $                 3.00 $            264,000
            10b.2 Modernize Staff Collaboration/Work Rooms                   500 sf  $             118.00 $              59,000
            10b.3 Reconfigure Staff Collaboration/Work Rooms                   500 sf  $             235.00 $            118,000
                                                                                  16 Next Generation Classroom Flexibility (Furniture)  $              375,000 $                    375,000
                                                                                   16a Flexible furniture (Per Classroom, Direct Cost)                     25 ea  $       15,000.00 $            375,000
          11 Library & Student Support Services            $           2,201,000 $                 2,927,000
            11a Elementary School Library/Innovation Lab
            11a.2 New Library/Innovation Lab Building                4,290 sf  $             406.00 $         1,742,000  17 Technology Infrastructure  $                       -  $                             -
            11a.5 Sitework & Site Improvements                4,290 sf  $               38.00 $            163,000  Not included in this Facilities Needs Assessment
            11d Learning Center
            11d.4 Reconfigure Learning Center                1,250 sf  $             237.00 $            296,000
                                                                                  Total Construction/Project Cost (2016$)         $         20,933,000  $27,717,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  511
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District