Page 545 - Facilities Master Plan 2016
P. 545

Lodi Unified School District                                            Lodi Unified School District
          Leroy Nichols Elementary School                                         Oakwood Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                        Project Cost Summary (2016$) - Leroy Nichols Elementary School           Project Cost Summary (2016$) - Oakwood Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
           16 Next Generation Classroom Flexibility (Furniture)  $              240,000 $                    240,000  01 Modernize & Reconfigure Aging Classrooms  $           1,766,000 $                 2,349,000
            16a Flexible furniture (Per Classroom, Direct Cost)                     16 ea  $       15,000.00 $            240,000  1b Replacement or repair of walls
                                                                                    1b.1 Replace walls                    3,180 sf  $               39.50 $            126,000
                                                                                    1b.2 Repair walls                  10,380 sf  $               12.60 $            131,000
           17 Technology Infrastructure                    $           32,000.00 $                 32,000.00  1c Replacement or repair of windows
             17c MDF and IDF data rooms with environmental control                  1c.1 Replace windows               13,560 sf  $               18.00 $            244,000
            (direct cost only)                            1 ea  $       32,000.00 $              32,000  1d Replacement or repair of doors (other than safety locks
                                                                                   @ classroom doors)
                                                                                    1d.1 Replace doors & hardware             13,560 sf  $               13.50 $            183,000
          Total Construction/Project Cost (2016$)          $         19,029,000  $25,220,000  1e Replacement or repair of floors
                                                                                    1e.1 Replace floors                13,560 sf  $               14.40 $            195,000
                                                                                   1f Replacement or repair of ceilings
          The following items are excluded from this budget:                        1f.1 Replace ceilings                 3,180 sf  $               27.00 $              86,000
           Utility hook-up fees & City connection fees.                             1f.2 Repair ceilings               10,380 sf  $                 8.10 $              84,000
           Offsite work and traffic signals.                                       1g Patch & Paint Interior/Exterior
           Land acquisition costs.                                                  1g.1 Patch & paint interior             13,560 sf  $                 3.10 $              42,000
           Hazardous material surveys, abatement, and disposal.                     1g.2 Patch & paint exterior             13,560 sf  $                 4.50 $              61,000
           Escalation (Costs are in 2016$ calculated to the end of the year).      1o Replace Existing Roofing             28,826 sf  $               20.93 $            603,000
                                                                                   1p Repair Existing Covered Walkways / Hallways                   825 sf  $               13.00 $              11,000
                                                                                  02 Existing Building Systems & Toilets          $           1,084,000 $                 1,442,000
                                                                                   2a HVAC system upgrades             13,560 sf  $               29.00 $            393,000
                                                                                   2b Lighting upgrades - new interior lighting & controls             13,560 sf  $               15.00 $            203,000
                                                                                   2c Electrical upgrades
                                                                                    2c.1 Upgrade electrical wiring & increase electrical
                                                                                    outlets                            13,560 sf  $                 9.00 $            122,000
                                                                                   2d Plumbing system upgrades             13,560 sf  $               11.00 $            149,000
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.1 Modernize Existing Restroom                1,429 sf  $               83.00 $            119,000
                                                                                   2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)             13,560 sf  $                 7.20 $              98,000
                                                                                  03 Site Utilities                               $           1,245,000 $                 1,656,000
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines           348,480 sf  $                 0.30 $            105,000
                                                                                   3b Updated sewer service lines           348,480 sf  $                 0.53 $            183,000
                                                                                   3c Updated water service lines           348,480 sf  $                 0.68 $            235,000
                                                                                   3d Updated electrical mains and distribution           348,480 sf  $                 0.90 $            314,000
                                                                                   3e Updated storm drainage system           348,480 sf  $                 0.68 $            235,000
                                                                                   3f Electrical Capacity Upgrades                        1 ls  $     172,500.00 $            173,000
                                                                                  04 Classrooms New Construction                  $           5,699,000 $                 7,580,000
                                                                                   4b New Construction - Classrooms
                                                                                    4b.1 Remove Portable Classrooms                     11 ea  $       11,000.00 $            121,000
                                                                                    4b.2 Relocate Portable Classrooms                        3 ea  $       25,000.00 $              75,000
                                                                                    4b.4 New Elementary Classroom Building (1-story)                1,056 sf  $             404.00 $            427,000


         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  516
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   540   541   542   543   544   545   546   547   548   549   550