Page 544 - Facilities Master Plan 2016
P. 544

Lodi Unified School District                                            Lodi Unified School District
          Leroy Nichols Elementary School                                         Leroy Nichols Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                        Project Cost Summary (2016$) - Leroy Nichols Elementary School          Project Cost Summary (2016$) - Leroy Nichols Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                    11a.5 Sitework & Site Improvements                4,290 sf  $               38.00 $            163,000
            4b.4 New Elementary Classroom Building (1-story)                5,280 sf  $             404.00 $         2,133,000  11d Learning Center
            4b.10 Sitework & Site Improvements                5,280 sf  $               38.00 $            201,000  11d.4 Reconfigure Learning Center                2,088 sf  $             237.00 $            495,000
            4d Student Collaboration Lab
            4d.1 New Student Collaboration Lab, 1- Story                1,056 sf  $             395.00 $            417,000
            4d.2 Sitework & Site Improvements                1,056 sf  $               38.00 $              40,000  12 Safety, Security & Campus Control  $           1,651,000 $                 2,196,000
                                                                                   12a  Remaining asbestos removal             30,344 sf  $                 4.00 $            121,000
                                                                                   12b Safety improvements to and/or new parent/bus drop-off areas and parking
          05 Maker Spaces & Science Labs                   $              700,000 $                    931,000  12b.1 New Parking Lot             22,000 sf  $               16.00 $            352,000
            5a ES Science / Creativity Labs                                         12b.3 Entry Plaza                     1,950 sf  $               26.00 $              51,000
                                                                                    12b.5 New Drop-off Area             12,150 sf  $               18.00 $            219,000
            5a.5 Reconfigure ES Science / Creativity Labs Building                 2,880 sf  $             243.00 $            700,000  12b.11 New concrete walkways                5,925 sf  $               15.00 $              89,000
                                                                                    12b.12 Repair concrete walkways                5,200 sf  $                 8.00 $              42,000
                                                                                   12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
          06 Electives                                     $                       -  $                             -  12e Safety locks at classroom doors                     30 ea  $             449.00 $              13,000
            Not included in this Facilities Needs Assessment                       12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
                                                                                   12g Marquee Sign                               1 ea  $       10,000.00 $              10,000
                                                                                   12h Fencing with controlled campus entrances
          07 Performing Arts Improvements                  $              750,000 $                    998,000  12h.2 Decorative Metal Fencing & Gates                   645 lf  $             252.00 $            163,000
            7a Music Lab                                                            12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $              27,000
            7a.4 New Music Lab                    1,540 sf  $             449.00 $            691,000  12i Fire safety equipment, fire alarms and emergency lighting
            7a.5 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000  12i.1 Fire Alarm System             30,344 sf  $                 5.40 $            164,000
                                                                                    12i.2 Emergency Lighting             30,344 sf  $                 1.40 $              42,000
                                                                                   12j New public address/emergency communication
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $           1,122,000 $                 1,492,000  systems              30,344 sf  $                 7.60 $            231,000
            8a Elementary/Middle School multipurpose rooms                         12k Intrusion alarms                30,344 sf  $                 1.80 $              55,000
            8a.2 Modernize Multipurpose Room                4,000 sf  $               99.00 $            396,000
            8c Food service areas
            8c.3 Reconfigure Food Service                1,230 sf  $             350.00 $            431,000  13 District Support Facilities  $                       -  $                             -
            8c.5 New Kitchen Equipment                1,230 sf  $               63.00 $              77,000  Not included in this Facilities Needs Assessment
            8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $              45,000
            8d New Lunch Shelters                 2,400 sf  $               72.00 $            173,000
                                                                                  14 Outdoor Learning Environments & Quads        $              403,000 $                    536,000
                                                                                   14a Main Student Quad
          09 Physical Education Improvements               $              933,000 $                 1,241,000  14a.2 New Main Student Quad                7,000 sf  $               20.70 $            145,000
            9c PE/Fitness Labs                                                     14b Learning Courts
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00 $            853,000  14b.2 New Learning Court             13,200 sf  $               19.55 $            258,000
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000
                                                                                  15 Exterior Play Spaces, Playfields & Hardcourts  $           1,458,000 $                 1,939,000
          10 Administration & Staff Support                $              844,000 $                 1,123,000  15a Kindergarten Play Yard
            10a Expanded, reorganized or relocated administration                   15a.1 New Rubberized Surface Play Area                3,000 sf  $               20.00 $              60,000
            spaces                                                                  15a.2 Relocate Kindergarten Play Apparatus                        1 ea  $       18,000.00 $              18,000
            10a.3 Reconfigure Administration                   840 sf  $             235.00 $            197,000  15a.3 Shade Structure                1,200 sf  $               90.00 $            108,000
            10a.4 New Administration                   975 sf  $             392.00 $            382,000  15a.6 New Hardcourts                8,250 sf  $               11.00 $              91,000
            10a.5 Sitework & Site Improvements                   975 sf  $               38.00 $              37,000  15b PE Play Yard & Hardcourts
            10b Staff Collaboration/Work Rooms                                      15a.1 New Rubberized Surface Play Area                4,500 sf  $               20.00 $              90,000
            10b.2 Modernize Staff Collaboration/Work Rooms                   936 sf  $             118.00 $            110,000  15b.3 Relocate Elementary Play Apparatus                        1 ea  $       18,000.00 $              18,000
            10b.3 Reconfigure Staff Collaboration/Work Rooms                   500 sf  $             235.00 $            118,000  15b.5 Resurface & Repair Hardcourts                8,550 sf  $                 5.00 $              43,000
                                                                                    15b.6 New Hardcourts               52,000 sf  $               11.00 $            572,000
                                                                                    15b.8 Basketball Court/Sports Equipment                        1 ls  $       25,333.33 $              25,000
          11 Library & Student Support Services            $           2,400,000 $                 3,192,000  15c Playfields
            11a Elementary School Library/Innovation Lab                            15c.1 Repair Playfields           144,375 sf  $                 3.00 $            433,000
            11a.2 New Library/Innovation Lab Building                4,290 sf  $             406.00 $         1,742,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  515
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District