Page 547 - Facilities Master Plan 2016
P. 547

Lodi Unified School District                                            Lodi Unified School District
          Oakwood Elementary School                                               Parklane Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                          Project Cost Summary (2016$) - Oakwood Elementary School               Project Cost Summary (2016$) - Parklane Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          Total Construction/Project Cost (2016$)          $         19,129,000  $25,328,000  01 Modernize & Reconfigure Aging Classrooms  $              813,000 $                 1,081,000
                                                                                   1b Replacement or repair of walls
                                                                                    1b.1 Replace walls                    1,920 sf  $               39.50 $              76,000
          The following items are excluded from this budget:                        1b.2 Repair walls                  14,880 sf  $               12.60 $            187,000
           Utility hook-up fees & City connection fees.                            1c Replacement or repair of windows
           Offsite work and traffic signals.                                        1c.2 Repair windows                16,800 sf  $                 3.60 $              60,000
           Land acquisition costs.                                                 1d Replacement or repair of doors (other than safety locks
           Hazardous material surveys, abatement, and disposal.                    @ classroom doors)
           Escalation (Costs are in 2016$ calculated to the end of the year).       1d.2 Repair doors & hardware             16,800 sf  $                 4.50 $              76,000
                                                                                   1e Replacement or repair of floors
                                                                                    1e.1 Replace floors                   1,920 sf  $               14.40 $              28,000
                                                                                    1e.2 Repair floors                 14,880 sf  $               10.80 $            161,000
                                                                                   1f Replacement or repair of ceilings
                                                                                    1f.1 Replace ceilings                 1,920 sf  $               27.00 $              52,000
                                                                                    1f.2 Repair ceilings               14,880 sf  $                 8.10 $            121,000
                                                                                   1g Patch & Paint Interior/Exterior
                                                                                    1g.1 Patch & paint interior             16,800 sf  $                 3.10 $              52,000
                                                                                  02 Existing Building Systems & Toilets          $           1,772,000 $                 2,357,000
                                                                                   2a HVAC system upgrades             16,800 sf  $               29.00 $            487,000
                                                                                   2b Lighting upgrades - new interior lighting & controls             16,800 sf  $               15.00 $            252,000
                                                                                   2c Electrical upgrades
                                                                                    2c.1 Upgrade electrical wiring & increase electrical
                                                                                    outlets                            16,800 sf  $                 9.00 $            151,000
                                                                                   2d Plumbing system upgrades             16,800 sf  $               11.00 $            185,000
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.1 Modernize Existing Restroom                1,400 sf  $               83.00 $            116,000
                                                                                    2e.3 New Restroom                        750 sf  $             556.00 $            417,000
                                                                                    2e.4 Sitework & Site Improvements                   750 sf  $               57.00 $              43,000
                                                                                   2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)             16,800 sf  $                 7.20 $            121,000
                                                                                  03 Site Utilities                               $              885,000 $                 1,177,000
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines           405,108 sf  $                 0.20 $              81,000
                                                                                   3b Updated sewer service lines           405,108 sf  $                 0.35 $            142,000
                                                                                   3c Updated water service lines           405,108 sf  $                 0.45 $            182,000
                                                                                   3d Updated electrical mains and distribution           405,108 sf  $                 0.90 $            365,000
                                                                                   3f Electrical Capacity Upgrades                        1 ls  $     115,000.00 $            115,000
                                                                                  04 Classrooms New Construction                  $           3,177,000 $                 4,225,000
                                                                                   4a New Construction - Pre-School, DK & Kindergarten
                                                                                    4a.2 New Pre-School, DK & Kindergarten Building                5,940 sf  $             395.00 $         2,346,000
                                                                                    4a.4 Sitework & Site Improvements                5,940 sf  $               38.00 $            226,000
                                                                                   4b New Construction - Classrooms
                                                                                    4b.1 Remove Portable Classrooms                        8 ea  $       11,000.00 $              88,000

         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  518
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   542   543   544   545   546   547   548   549   550   551   552