Page 551 - Facilities Master Plan 2016
P. 551

Lodi Unified School District                                           Lodi Unified School District
          Erma B. Reese Elementary School                                        Erma B. Reese Elementary School
          Facilities Master Plan - Total Program Cost                            Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16  Opinion of Probable Cost                                     19-Apr-16
                        Project Cost Summary (2016$) - Erma B. Reese Elementary School         Project Cost Summary (2016$) - Erma B. Reese Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                   4b.10 Sitework & Site Improvements             16,896 sf  $               38.00 $             642,000
          01 Modernize & Reconfigure Aging Classrooms     $             2,385,000 $                 3,172,000  4d Student Collaboration Lab
           1b Replacement or repair of walls                                       4d.1 New Student Collaboration Lab, 1- Story                1,584 sf  $             395.00 $             626,000
            1b.1 Replace walls                    6,750 sf  $               39.50 $             267,000  4d.2 Sitework & Site Improvements                1,584 sf  $               38.00 $               60,000
            1b.2 Repair walls                     9,600 sf  $               12.60 $             121,000
           1c Replacement or repair of windows
            1c.1 Replace windows               16,350 sf  $               18.00 $             294,000  05 Maker Spaces & Science Labs  $             1,472,000 $                 1,958,000
           1d Replacement or repair of doors (other than safety locks              5a ES Science / Creativity Labs
           @ classroom doors)                                                      5a.6 New ES Science / Creativity Labs Building                 3,080 sf  $             440.00 $          1,355,000
            1d.1 Replace doors & hardware             16,350 sf  $               13.50 $             221,000  5a.7 Sitework & Site Improvements                3,080 sf  $               38.00 $             117,000
           1e Replacement or repair of floors
            1e.1 Replace floors                   6,750 sf  $               14.40 $               97,000
            1e.2 Repair floors                    9,600 sf  $               10.80 $             104,000  06 Electives             $                         -  $                             -
           1f Replacement or repair of ceilings                                    Not included in this Facilities Needs Assessment
            1f.1 Replace ceilings                 6,750 sf  $               27.00 $             182,000
            1f.2 Repair ceilings                  9,600 sf  $                 8.10 $               78,000
           1g Patch & Paint Interior/Exterior                                    07 Performing Arts Improvements                  $                750,000 $                    998,000
            1g.1 Patch & paint interior             16,350 sf  $                 3.10 $               51,000  7a Music Lab
            1g.2 Patch & paint exterior             16,350 sf  $                 4.50 $               74,000  7a.4 New Music Lab                1,540 sf  $             449.00 $             691,000
           1o Replace Existing Roofing             35,410 sf  $               20.93 $             741,000  7a.5 Sitework & Site Improvements                1,540 sf  $               38.00 $               59,000
           1p Repair Existing Covered Walkways / Hallways             11,900 sf  $               13.00 $             155,000
                                                                                 08 Multi-Purpose Room / Food Service Improvements & Student Dining  $             1,295,000 $                 1,722,000
          02 Existing Building Systems & Toilets          $             1,529,000 $                 2,034,000  8a Elementary/Middle School multipurpose rooms
           2a HVAC system upgrades             16,350 sf  $               29.00 $             474,000  8a.2 Modernize Multipurpose Room                3,500 sf  $               99.00 $             347,000
                                                                                    8a.4 New Multipurpose Room                1,125 sf  $             494.00 $             556,000
           2b Lighting upgrades - new interior lighting & controls             16,350 sf  $               15.00 $             245,000  8a.5 Sitework & Site Improvements                1,125 sf  $               38.00 $               43,000
           2c Electrical upgrades                                                  8c Food service areas
            2c.1 Upgrade electrical wiring & increase electrical                    8c.2 Modernize Food Service                   750 sf  $             175.00 $             131,000
            outlets                            16,350 sf  $                 9.00 $             147,000  8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $               45,000
           2d Plumbing system upgrades             16,350 sf  $               11.00 $             180,000  8d New Lunch Shelters                2,400 sf  $               72.00 $             173,000
           2e Replace aging plumbing, upgrade and/or expand
           restroom facilities
            2e.1 Modernize Existing Restroom                1,200 sf  $               83.00 $             100,000  09 Physical Education Improvements  $                933,000 $                 1,241,000
            2e.3 New Restroom                        432 sf  $             556.00 $             240,000
            2e.4 Sitework & Site Improvements                   432 sf  $               57.00 $               25,000  9c PE/Fitness Labs
           2f Energy-efficient building systems and controls (EMS                   9c.4 New PE/Fitness Labs                2,112 sf  $             404.00 $             853,000
           system, per sf of Bldg)             16,350 sf  $                 7.20 $             118,000  9c.5 Sitework & Site Improvements                2,112 sf  $               38.00 $               80,000
                                                                                 10 Administration & Staff Support                $             1,702,000 $                 2,264,000
          03 Site Utilities                               $             1,055,000 $                 1,403,000
           (For entire campus and site)                                            10a Expanded, reorganized or relocated administration
                                                                                   spaces
           3a Updated gas service lines           399,881 sf  $                 0.20 $               80,000  10a.4 New Administration                1,980 sf  $             392.00 $             776,000
           3b Updated sewer service lines           399,881 sf  $                 0.35 $             140,000
                                                                                   10a.5 Sitework & Site Improvements
           3c Updated water service lines           399,881 sf  $                 0.45 $             180,000  10b Staff Collaboration/Work Rooms                1,980 sf  $               38.00 $               75,000
           3d Updated electrical mains and distribution           399,881 sf  $                 0.90 $             360,000  10b.4 New Staff Collaboration/Work Rooms                1,980 sf  $             392.00 $             776,000
           3e Updated storm drainage system           399,881 sf  $                 0.45 $             180,000  10b.5 Sitework & Site Improvements                1,980 sf  $               38.00 $               75,000
           3f Electrical Capacity Upgrades                        1 ls  $     115,000.00 $             115,000
                                                                                 11 Library & Student Support Services            $             2,310,000 $                 3,072,000
          04 Classrooms New Construction                  $             6,954,000 $                 9,249,000  11a Elementary School Library/Innovation Lab
           4b New Construction - Classrooms                                        11a.2 New Library/Innovation Lab Building                4,290 sf  $             406.00 $          1,742,000
            4b.1 Remove Portable Classrooms                     15 ea  $       11,000.00 $             165,000
                                                                                   11a.5 Sitework & Site Improvements                4,290 sf  $               38.00 $             163,000
            4b.4 New Elementary Classroom Building (1-story)             16,896 sf  $             323.20 $          5,461,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  522
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   546   547   548   549   550   551   552   553   554   555   556