Page 555 - Facilities Master Plan 2016
P. 555

Lodi Unified School District                                            Lodi Unified School District
          Sutherland Elementary School                                            Sutherland Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Sutherland Elementary School            Project Cost Summary (2016$) - Sutherland Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            4b.10 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000
            4d Student Collaboration Lab                                          12 Safety, Security & Campus Control            $           1,656,000 $                 2,202,000
            4d.1 New Student Collaboration Lab, 1- Story                   528 sf  $             395.00 $            209,000  12b Safety improvements to and/or new parent/bus drop-off areas and parking
            4d.2 Sitework & Site Improvements                   528 sf  $               38.00 $              20,000  12b.1 New Parking Lot             38,350 sf  $               16.00 $            614,000
                                                                                    12b.5 New Drop-off Area                9,800 sf  $               18.00 $            176,000
                                                                                    12b.11 New concrete walkways                4,300 sf  $               15.00 $              65,000
          05 Maker Spaces & Science Labs                   $              700,000 $                    931,000  12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
            5a ES Science / Creativity Labs                                        12e Safety locks at classroom doors                     35 ea  $             449.00 $              16,000
                                                                                   12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
            5a.5 Reconfigure ES Science / Creativity Labs Building                 2,880 sf  $             243.00 $            700,000  12g Marquee Sign                        1 ea  $       10,000.00 $              10,000
                                                                                   12h Fencing with controlled campus entrances
                                                                                    12h.2 Decorative Metal Fencing & Gates                   440 lf  $             252.00 $            111,000
          06 Electives                                     $                       -  $                             -  12i Fire safety equipment, fire alarms and emergency lighting
            Not included in this Facilities Needs Assessment                        12i.1 Fire Alarm System             36,549 sf  $                 5.40 $            197,000
                                                                                    12i.2 Emergency Lighting             36,549 sf  $                 1.40 $              51,000
                                                                                   12j New public address/emergency communication
          07 Performing Arts Improvements                  $              750,000 $                    998,000  systems              36,549 sf  $                 7.60 $            278,000
            7a Music Lab                                                           12k Intrusion alarms                36,549 sf  $                 1.80 $              66,000
            7a.4 New Music Lab                    1,540 sf  $             449.00 $            691,000
            7a.5 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000
                                                                                  13 District Support Facilities                  $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $              676,000 $                    899,000
            8a Elementary/Middle School multipurpose rooms
            8a.2 Modernize Multipurpose Room                4,680 sf  $               99.00 $            463,000  14 Outdoor Learning Environments & Quads  $              152,000 $                    202,000
            8c Food service areas                                                  14b Learning Courts
            8c.2 Modernize Food Service                   960 sf  $             175.00 $            168,000  14b.2 New Learning Court                6,600 sf  $               23.00 $            152,000
            8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $              45,000
                                                                                  15 Exterior Play Spaces, Playfields & Hardcourts  $           1,211,000 $                 1,611,000
          09 Physical Education Improvements               $              933,000 $                 1,241,000  15a Kindergarten Play Yard
            9c PE/Fitness Labs                                                      15a.1 New Rubberized Surface Play Area                1,750 sf  $               20.00 $              35,000
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00 $            853,000  15a.3 Shade Structure                1,200 sf  $               90.00 $            108,000
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000  15b PE Play Yard & Hardcourts
                                                                                    15a.1 New Rubberized Surface Play Area                4,700 sf  $               20.00 $              94,000
                                                                                    15b.4 Shade Structure                 2,400 sf  $               90.00 $            216,000
          10 Administration & Staff Support                $              333,000 $                    443,000  15b.5 Resurface & Repair Hardcourts             62,450 sf  $                 5.00 $            312,000
            10a Expanded, reorganized or relocated administration                  15c Playfields
            spaces                                                                  15c.1 Repair Playfields           148,725 sf  $                 3.00 $            446,000
            10a.2 Modernize Administration                2,030 sf  $             118.00 $            240,000
            10b Staff Collaboration/Work Rooms
            10b.2 Modernize Staff Collaboration/Work Rooms                   784 sf  $             118.00 $              93,000  16 Next Generation Classroom Flexibility (Furniture)  $              315,000 $                    315,000
                                                                                   16a Flexible furniture (Per Classroom, Direct Cost)                     21 ea  $       15,000.00 $            315,000
          11 Library & Student Support Services            $           1,263,000 $                 1,680,000
            11a Elementary School Library/Innovation Lab                          17 Technology Infrastructure                    $                       -  $                             -
            11a.4 Reconfigure Library/Innovation Lab Building                3,760 sf  $             244.00 $            917,000  Not included in this Facilities Needs Assessment
            11d Learning Center
            11d.3 Modernize Learning Center                   600 sf  $             119.00 $              71,000
            11d.4 Reconfigure Learning Center                1,160 sf  $             237.00 $            275,000  Total Construction/Project Cost (2016$)  $         12,778,000  $16,891,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  526
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District