Page 560 - Facilities Master Plan 2016
P. 560

Lodi Unified School District                                            Lodi Unified School District
          Wagner Holt Elementary School                                           Wagner Holt Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Wagner Holt Elementary School           Project Cost Summary (2016$) - Wagner Holt Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                   4b New Construction - Classrooms
          01 Modernize & Reconfigure Aging Classrooms      $           1,683,000 $                 2,238,000  4b.1 Remove Portable Classrooms                        1 ea  $       11,000.00 $              11,000
            1b Replacement or repair of walls                                       4b.2 Relocate Portable Classrooms                        1 ea  $       25,000.00 $              25,000
            1b.1 Replace walls                    1,920 sf  $               39.50 $              76,000  4b.3 Demolish Existing Buildings                   840 sf  $               22.00 $              18,000
            1b.2 Repair walls                  14,700 sf  $               12.60 $            185,000
            1c Replacement or repair of windows                                     4b.4 New Elementary Classroom Building (1-story)                1,200 sf  $             404.00 $            485,000
            1c.2 Repair windows                16,620 sf  $                 3.60 $              60,000  4b.10 Sitework & Site Improvements                1,200 sf  $               38.00 $              46,000
            1d Replacement or repair of doors (other than safety locks
            @ classroom doors)
            1d.2 Repair doors & hardware             16,620 sf  $                 4.50 $              75,000  05 Maker Spaces & Science Labs  $           1,673,000 $                 2,225,000
            1e Replacement or repair of floors                                     5a ES Science / Creativity Labs
            1e.1 Replace floors                   1,920 sf  $               14.40 $              28,000  5a.6 New ES Science / Creativity Labs Building                 3,500 sf  $             440.00 $         1,540,000
            1e.2 Repair floors                 14,700 sf  $               10.80 $            159,000  5a.7 Sitework & Site Improvements                3,500 sf  $               38.00 $            133,000
            1f Replacement or repair of ceilings
            1f.1 Replace ceilings                 1,920 sf  $               27.00 $              52,000
            1f.2 Repair ceilings               14,700 sf  $                 8.10 $            119,000  06 Electives               $                       -  $                             -
            1g Patch & Paint Interior/Exterior                                     Not included in this Facilities Needs Assessment
            1g.1 Patch & paint interior             16,620 sf  $                 3.10 $              52,000
            1g.2 Patch & paint exterior             16,620 sf  $                 4.50 $              75,000
            1o Replace Existing Roofing             35,725 sf  $               20.93 $            748,000  07 Performing Arts Improvements  $              853,000 $                 1,134,000
            1p Repair Existing Covered Walkways / Hallways                4,176 sf  $               13.00 $              54,000  7a Music Lab
                                                                                    7a.4 New Music Lab                    1,750 sf  $             449.00 $            786,000
                                                                                    7a.5 Sitework & Site Improvements                1,750 sf  $               38.00 $              67,000
          02 Existing Building Systems & Toilets           $           1,271,000 $                 1,690,000
            2a HVAC system upgrades             16,620 sf  $               29.00 $            482,000
                                                                                  08 Multi-Purpose Room / Food Service Improvements & Student Dining  $              854,000 $                 1,136,000
            2b Lighting upgrades - new interior lighting & controls             16,620 sf  $               15.00 $            249,000  8a Elementary/Middle School multipurpose rooms
            2c Electrical upgrades                                                  8a.2 Modernize Multipurpose Room                4,660 sf  $               99.00 $            461,000
            2c.1 Upgrade electrical wiring & increase electrical                   8c Food service areas
            outlets                            16,620 sf  $                 9.00 $            150,000  8c.2 Modernize Food Service                1,000 sf  $             175.00 $            175,000
            2d Plumbing system upgrades             16,620 sf  $               11.00 $            183,000  8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $              45,000
            2e Replace aging plumbing, upgrade and/or expand                       8d New Lunch Shelters                  2,400 sf  $               72.00 $            173,000
            restroom facilities
            2e.1 Modernize Existing Restroom                1,050 sf  $               83.00 $              87,000
            2f Energy-efficient building systems and controls (EMS                09 Physical Education Improvements              $           1,061,000 $                 1,411,000
            system, per sf of Bldg)             16,620 sf  $                 7.20 $            120,000
                                                                                   9c PE/Fitness Labs
                                                                                    9c.4 New PE/Fitness Labs                2,400 sf  $             404.00 $            970,000
                                                                                    9c.5 Sitework & Site Improvements                2,400 sf  $               38.00 $              91,000
          03 Site Utilities                                $              591,000 $                    786,000
            (For entire campus and site)
            3a Updated gas service lines           415,215 sf  $                 0.13 $              53,000  10 Administration & Staff Support  $              367,000 $                    488,000
            3b Updated sewer service lines           415,215 sf  $                 0.21 $              87,000  10a Expanded, reorganized or relocated administration
            3c Updated water service lines           415,215 sf  $                 0.27 $            112,000  spaces
            3d Updated electrical mains and distribution           415,215 sf  $                 0.54 $            224,000  10a.2 Modernize Administration                2,100 sf  $             118.00 $            248,000
            3f Electrical Capacity Upgrades                        1 ls  $     115,000.00 $            115,000  10b Staff Collaboration/Work Rooms
                                                                                    10b.2 Modernize Staff Collaboration/Work Rooms                1,009 sf  $             118.00 $            119,000
          04 Classrooms New Construction                   $           1,871,000 $                 2,488,000
                                                                                  11 Library & Student Support Services           $           1,184,000 $                 1,575,000
            4a New Construction - Pre-School, DK & Kindergarten
                                                                                   11a Elementary School Library/Innovation Lab
                                                                                    11a.4 Reconfigure Library/Innovation Lab Building                3,760 sf  $             244.00 $            917,000
            4a.2 New Pre-School, DK & Kindergarten Building                2,970 sf  $             395.00 $         1,173,000
            4a.4 Sitework & Site Improvements                2,970 sf  $               38.00 $            113,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  531
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   555   556   557   558   559   560   561   562   563   564   565