Page 561 - Facilities Master Plan 2016
P. 561

Lodi Unified School District                                            Lodi Unified School District
          Wagner Holt Elementary School                                           Wagner Holt Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Wagner Holt Elementary School           Project Cost Summary (2016$) - Wagner Holt Elementary School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            11d Learning Center
            11d.3 Modernize Learning Center                   450 sf  $             119.00 $              54,000  17 Technology Infrastructure  $                       -  $                             -
            11d.4 Reconfigure Learning Center                   900 sf  $             237.00 $            213,000  Not included in this Facilities Needs Assessment
                                    .
          12 Safety, Security & Campus Control             $           1,834,000 $                 2,439,000  Total Construction/Project Cost (2016$)  $         14,693,000  $19,431,000
            12b Safety improvements to and/or new parent/bus drop-off areas and parking
            12b.1 New Parking Lot              33,025 sf  $               16.00 $            528,000
            12b.5 New Drop-off Area                7,600 sf  $               18.00 $            137,000  The following items are excluded from this budget:
            12b.9 Repair existing Parking Lot             11,475 sf  $                 6.30 $              72,000  Utility hook-up fees & City connection fees.
            12b.11 New concrete walkways                6,750 sf  $               15.00 $            101,000  Offsite work and traffic signals.
            12b.12 Repair concrete walkways                4,176 sf  $                 8.00 $              33,000  Land acquisition costs.
            12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000  Hazardous material surveys, abatement, and disposal.
            12e Safety locks at classroom doors                     40 ea  $             449.00 $              18,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000
            12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                1,288 lf  $             252.00 $            325,000
            12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $              27,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System             31,549 sf  $                 5.40 $            170,000
            12i.2 Emergency Lighting             31,549 sf  $                 1.40 $              44,000
            12j New public address/emergency communication
            systems                            31,549 sf  $                 7.60 $            240,000
            12k Intrusion alarms               31,549 sf  $                 1.80 $              57,000
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $              138,000 $                    184,000
            14b Learning Courts
            14b.2 New Learning Court                6,000 sf  $               23.00 $            138,000
           15 Exterior Play Spaces, Playfields & Hardcourts  $              983,000 $                 1,307,000
            15a Kindergarten Play Yard
            15a.1 New Rubberized Surface Play Area                1,750 sf  $               20.00 $              35,000
            15a.3 Shade Structure                 1,200 sf  $               90.00 $            108,000
            15b PE Play Yard & Hardcourts
            15a.1 New Rubberized Surface Play Area                4,500 sf  $               20.00 $              90,000
            15b.5 Resurface & Repair Hardcourts             41,300 sf  $                 5.00 $            207,000
            15b.6 New Hardcourts               17,625 sf  $               11.00 $            194,000
            15c Playfields
            15c.1 Repair Playfields           116,350 sf  $                 3.00 $            349,000
           16 Next Generation Classroom Flexibility (Furniture)  $              330,000 $                    330,000
            16a Flexible furniture (Per Classroom, Direct Cost)                     22 ea  $       15,000.00 $            330,000





         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  532
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District