Page 556 - Facilities Master Plan 2016
P. 556

Lodi Unified School District                                            Lodi Unified School District
          Sutherland Elementary School                                            Victor Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Sutherland Elementary School              Project Cost Summary (2016$) - Victor Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          The following items are excluded from this budget:                      01 Modernize & Reconfigure Aging Classrooms     $              586,000 $                    779,000
           Utility hook-up fees & City connection fees.                            1b Replacement or repair of walls
           Offsite work and traffic signals.                                        1b.2 Repair walls                     5,460 sf  $               12.60 $              69,000
           Land acquisition costs.                                                 1c Replacement or repair of windows
           Hazardous material surveys, abatement, and disposal.                     1c.2 Repair windows                   5,460 sf  $                 3.60 $              20,000
           Escalation (Costs are in 2016$ calculated to the end of the year).      1d Replacement or repair of doors (other than safety locks
                                                                                   @ classroom doors)
                                                                                    1d.2 Repair doors & hardware                5,460 sf  $                 4.50 $              25,000
                                                                                   1e Replacement or repair of floors
                                                                                    1e.2 Repair floors                    5,460 sf  $               10.80 $              59,000
                                                                                   1f Replacement or repair of ceilings
                                                                                    1f.2 Repair ceilings                  5,460 sf  $                 8.10 $              44,000
                                                                                   1g Patch & Paint Interior/Exterior
                                                                                    1g.1 Patch & paint interior                5,460 sf  $                 3.10 $              17,000
                                                                                    1g.2 Patch & paint exterior                5,460 sf  $                 4.50 $              25,000
                                                                                   1o Replace Existing Roofing             15,635 sf  $               20.93 $            327,000
                                                                                  02 Existing Building Systems & Toilets          $              916,000 $                 1,218,000
                                                                                   2a HVAC system upgrades                5,460 sf  $               29.00 $            158,000
                                                                                   2b Lighting upgrades - new interior lighting & controls                5,460 sf  $               15.00 $              82,000
                                                                                   2c Electrical upgrades
                                                                                    2c.1 Upgrade electrical wiring & increase electrical
                                                                                    outlets                               5,460 sf  $                 9.00 $              49,000
                                                                                   2d Plumbing system upgrades                5,460 sf  $               11.00 $              60,000
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.1 Modernize Existing Restroom                   825 sf  $               83.00 $              68,000
                                                                                    2e.3 New Restroom                        750 sf  $             556.00 $            417,000
                                                                                    2e.4 Sitework & Site Improvements                   750 sf  $               57.00 $              43,000
                                                                                   2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)                5,460 sf  $                 7.20 $              39,000
                                                                                  03 Site Utilities                               $              713,000 $                    948,000
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines           696,960 sf  $                 0.08 $              56,000
                                                                                   3b Updated sewer service lines           696,960 sf  $                 0.14 $              98,000
                                                                                   3c Updated water service lines           696,960 sf  $                 0.18 $            125,000
                                                                                   3d Updated electrical mains and distribution           696,960 sf  $                 0.36 $            251,000
                                                                                   3e Updated storm drainage system           696,960 sf  $                 0.18 $            125,000
                                                                                   3f Electrical Capacity Upgrades                        1 ls  $       57,500.00 $              58,000
                                                                                  04 Classrooms New Construction                  $           1,662,000 $                 2,210,000
                                                                                   4b New Construction - Classrooms
                                                                                    4b.1 Remove Portable Classrooms                        3 ea  $       11,000.00 $              33,000
                                                                                    4b.4 New Elementary Classroom Building (1-story)                3,168 sf  $             404.00 $         1,280,000
                                                                                    4b.10 Sitework & Site Improvements                3,168 sf  $               38.00 $            120,000



         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  527
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District