Page 557 - Facilities Master Plan 2016
P. 557

Lodi Unified School District                                            Lodi Unified School District
          Victor Elementary School                                                Victor Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                          Project Cost Summary (2016$) - Victor Elementary School                 Project Cost Summary (2016$) - Victor Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            4d Student Collaboration Lab                                            12b.11 New concrete walkways                2,600 sf  $               15.00 $              39,000
            4d.1 New Student Collaboration Lab, 1- Story                   528 sf  $             395.00 $            209,000  12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
            4d.2 Sitework & Site Improvements                   528 sf  $               38.00 $              20,000  12e Safety locks at classroom doors                     15 ea  $             449.00 $                 7,000
                                                                                   12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
                                                                                   12g Marquee Sign                               1 ea  $       10,000.00 $              10,000
          05 Maker Spaces & Science Labs                   $              737,000 $                    980,000  12h Fencing with controlled campus entrances
            5a ES Science / Creativity Labs                                         12h.2 Decorative Metal Fencing & Gates                   290 lf  $             252.00 $              73,000
            5a.6 New ES Science / Creativity Labs Building                 1,540 sf  $             440.00 $            678,000  12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $              27,000
            5a.7 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000  12i Fire safety equipment, fire alarms and emergency lighting
                                                                                    12i.1 Fire Alarm System             15,635 sf  $                 5.40 $              84,000
                                                                                    12i.2 Emergency Lighting             15,635 sf  $                 1.40 $              22,000
          06 Electives                                     $                       -  $                             -  12j New public address/emergency communication
            Not included in this Facilities Needs Assessment                       systems                             15,635 sf  $                 7.60 $            119,000
                                                                                   12k Intrusion alarms                15,635 sf  $                 1.80 $              28,000
          07 Performing Arts Improvements                  $                       -  $                             -
            Not included in this Facilities Needs Assessment                      13 District Support Facilities                  $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $              992,000 $                 1,319,000
            8a Elementary/Middle School multipurpose rooms                        14 Outdoor Learning Environments & Quads        $                 66,000 $                      88,000
            8a.2 Modernize Multipurpose Room                1,400 sf  $               99.00 $            139,000  14b Learning Courts
            8a.4 New Multipurpose Room                1,225 sf  $             494.00 $            605,000  14b.2 New Learning Court                3,000 sf  $               21.85 $              66,000
            8a.5 Sitework & Site Improvements                1,225 sf  $               38.00 $              47,000
            8c Food service areas
            8c.2 Modernize Food Service                   400 sf  $             175.00 $              70,000  15 Exterior Play Spaces, Playfields & Hardcourts  $              603,000 $                    802,000
            8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $              45,000  15a Kindergarten Play Yard
            8d New Lunch Shelters                 1,200 sf  $               72.00 $              86,000  15a.1 New Rubberized Surface Play Area                1,200 sf  $               20.00 $              24,000
                                                                                   15b PE Play Yard & Hardcourts
                                                                                    15a.1 New Rubberized Surface Play Area                1,500 sf  $               20.00 $              30,000
          09 Physical Education Improvements               $              933,000 $                 1,241,000  15b.5 Resurface & Repair Hardcourts             29,700 sf  $                 5.00 $            149,000
            9c PE/Fitness Labs                                                      15b.8 Basketball Court/Sports Equipment                        1 ls  $       12,666.67 $              13,000
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00 $            853,000  15c Playfields
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000  15c.1 Repair Playfields           129,000 sf  $                 3.00 $            387,000
          10 Administration & Staff Support                $              165,000 $                    219,000  16 Next Generation Classroom Flexibility (Furniture)  $              120,000 $                    120,000
            10a Expanded, reorganized or relocated administration                  16a Flexible furniture (Per Classroom, Direct Cost)                        8 ea  $       15,000.00 $            120,000
            spaces
            10a.2 Modernize Administration                1,400 sf  $             118.00 $            165,000
                                                                                  17 Technology Infrastructure                    $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
          11 Library & Student Support Services            $           1,487,000 $                 1,978,000
            11a Elementary School Library/Innovation Lab
            11a.4 Reconfigure Library/Innovation Lab Building                4,200 sf  $             244.00 $         1,025,000  Total Construction/Project Cost (2016$)  $           9,823,000  $13,023,000
            11d Learning Center
            11d.4 Reconfigure Learning Center                1,950 sf  $             237.00 $            462,000
                                                                                  The following items are excluded from this budget:
                                                                                  Utility hook-up fees & City connection fees.
          12 Safety, Security & Campus Control             $              843,000 $                 1,121,000  Offsite work and traffic signals.
            12b Safety improvements to and/or new parent/bus drop-off areas and parking  Land acquisition costs.
            12b.1 New Parking Lot              10,000 sf  $               16.00 $            160,000  Hazardous material surveys, abatement, and disposal.
            12b.5 New Drop-off Area                7,000 sf  $               18.00 $            126,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            12b.9 Repair existing Parking Lot             12,000 sf  $                 6.30 $              76,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  528
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District