Lodi Unified School District                                            Lodi Unified School District
          Manlio Silva Elementary School                                          Sutherland Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Manlio Silva Elementary School          Project Cost Summary (2016$) - Sutherland Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            15c Playfields
            15c.1 Repair Playfields           128,800 sf  $                 3.00 $            386,000  01 Modernize & Reconfigure Aging Classrooms  $              946,000 $                 1,258,000
            15d Baseball/Softball Fields                                           1b Replacement or repair of walls
            15d.4 Backstops, per field                        1 ea  $       27,000.00 $              27,000  1b.1 Replace walls                    960 sf  $               39.50 $              38,000
                                                                                    1b.2 Repair walls                  18,060 sf  $               12.60 $            228,000
                                                                                   1c Replacement or repair of windows
           16 Next Generation Classroom Flexibility (Furniture)  $              233,000 $                    233,000  1c.2 Repair windows             19,020 sf  $                 3.60 $              68,000
            16a Flexible furniture (Per Classroom, Direct Cost)                     31 ea  $         7,500.00 $            233,000  1d Replacement or repair of doors (other than safety locks
                                                                                   @ classroom doors)
                                                                                    1d.2 Repair doors & hardware             19,020 sf  $                 4.50 $              86,000
           17 Technology Infrastructure                    $                       -  $                             -  1e Replacement or repair of floors
            Not included in this Facilities Needs Assessment                        1e.1 Replace floors                      960 sf  $               14.40 $              14,000
                                                                                    1e.2 Repair floors                 18,060 sf  $               10.80 $            195,000
                                                                                   1f Replacement or repair of ceilings
          Total Construction/Project Cost (2016$)          $           8,900,000  $11,761,000  1f.1 Replace ceilings                   960 sf  $               27.00 $              26,000
                                                                                    1f.2 Repair ceilings               18,060 sf  $                 8.10 $            146,000
                                                                                   1g Patch & Paint Interior/Exterior
          The following items are excluded from this budget:                        1g.1 Patch & paint interior             19,020 sf  $                 3.10 $              59,000
           Utility hook-up fees & City connection fees.                             1g.2 Patch & paint exterior             19,020 sf  $                 4.50 $              86,000
           Offsite work and traffic signals.
           Land acquisition costs.
           Hazardous material surveys, abatement, and disposal.                   02 Existing Building Systems & Toilets          $           1,410,000 $                 1,875,000
           Escalation (Costs are in 2016$ calculated to the end of the year).      2a HVAC system upgrades             19,020 sf  $               29.00 $            552,000
                                                                                   2b Lighting upgrades - new interior lighting & controls             19,020 sf  $               15.00 $            285,000
                                                                                   2c Electrical upgrades
                                                                                    2c.1 Upgrade electrical wiring & increase electrical
                                                                                    outlets                            19,020 sf  $                 9.00 $            171,000
                                                                                   2d Plumbing system upgrades             19,020 sf  $               11.00 $            209,000
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.1 Modernize Existing Restroom                   675 sf  $               83.00 $              56,000
                                                                                   2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)             19,020 sf  $                 7.20 $            137,000
                                                                                  03 Site Utilities                               $              610,000 $                    811,000
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines           431,244 sf  $                 0.13 $              55,000
                                                                                   3b Updated sewer service lines           431,244 sf  $                 0.21 $              91,000
                                                                                   3c Updated water service lines           431,244 sf  $                 0.27 $            116,000
                                                                                   3d Updated electrical mains and distribution           431,244 sf  $                 0.54 $            233,000
                                                                                   3f Electrical Capacity Upgrades                        1 ls  $     115,000.00 $            115,000
                                                                                  04 Classrooms New Construction                  $           1,823,000 $                 2,425,000
                                                                                   4a New Construction - Pre-School, DK & Kindergarten
                                                                                    4a.2 New Pre-School, DK & Kindergarten Building                1,485 sf  $             395.00 $            587,000
                                                                                    4a.4 Sitework & Site Improvements                1,485 sf  $               38.00 $              56,000
                                                                                   4b New Construction - Classrooms
                                                                                    4b.3 Demolish Existing Buildings                   840 sf  $               22.00 $              18,000
                                                                                    4b.4 New Elementary Classroom Building (1-story)                2,112 sf  $             404.00 $            853,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  525
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   549   550   551   552   553   554   555   556   557   558   559