          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                        Project Cost Summary (2016$) - Podesta Ranch Elementary School          Project Cost Summary (2016$) - Podesta Ranch Elementary School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          09 Physical Education Improvements               $              933,000 $                 1,241,000  17 Technology Infrastructure  $                       -  $                             -
            9c PE/Fitness Labs                                                     Not included in this Facilities Needs Assessment
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00 $            853,000
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000
                                                                                  Total Construction/Project Cost (2016$)         $         10,829,000  $14,341,000
          10 Administration & Staff Support                $              176,000 $                    234,000
            10a Expanded, reorganized or relocated administration                 The following items are excluded from this budget:
            spaces                                                                 Utility hook-up fees & City connection fees.
            10a.3 Reconfigure Administration                   750 sf  $             235.00 $            176,000  Offsite work and traffic signals.
                                                                                   Land acquisition costs.
                                                                                   Hazardous material surveys, abatement, and disposal.
          11 Library & Student Support Services            $              929,000 $                 1,236,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            11d Learning Center
            11d.2 New Learning Center                2,145 sf  $             395.00 $            847,000
            11d.5 Sitework & Site Improvements                2,145 sf  $               38.00 $              82,000
          12 Safety, Security & Campus Control             $                 38,000 $                      51,000
            12b Safety improvements to and/or new parent/bus drop-off areas and parking
            12e Safety locks at classroom doors                     35 ea  $             449.00 $              16,000
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System                   750 sf  $                 5.40 $                 4,000
            12i.2 Emergency Lighting                   750 sf  $                 1.40 $                 1,000
            12j New public address/emergency communication
            systems                                  750 sf  $                 7.60 $                 6,000
            12k Intrusion alarms                     750 sf  $                 1.80 $                 1,000
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $                       -  $                             -
            Not included in this Facilities Needs Assessment

           15 Exterior Play Spaces, Playfields & Hardcourts  $              332,000 $                    442,000
            15a Kindergarten Play Yard
            15a.1 New Rubberized Surface Play Area                2,025 sf  $               20.00 $              41,000
            15a.3 Shade Structure                 1,200 sf  $               90.00 $            108,000
            15b PE Play Yard & Hardcourts
            15a.1 New Rubberized Surface Play Area                6,000 sf  $               20.00 $            120,000
            15b.2 Elementary Play Apparatus                        1 ea  $       63,000.00 $              63,000
           16 Next Generation Classroom Flexibility (Furniture)  $              195,000 $                    195,000
            16a Flexible furniture (Per Classroom, Direct Cost)                     26 ea  $         7,500.00 $            195,000





         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  521
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   545   546   547   548   549   550   551   552   553   554   555