Page 535 - Facilities Master Plan 2016
P. 535

Lodi Unified School District                                            Lodi Unified School District
          Lockeford Elementary School                                             Lockeford Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Lockeford Elementary School              Project Cost Summary (2016$) - Lockeford Elementary School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            12b.11 New concrete walkways                4,000 sf  $               15.00 $              60,000
            12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000  The following items are excluded from this budget:
            12e Safety locks at classroom doors                     25 ea  $             449.00 $              11,000  Utility hook-up fees & City connection fees.
            12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000  Offsite work and traffic signals.
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000  Land acquisition costs.
            12h Fencing with controlled campus entrances                           Hazardous material surveys, abatement, and disposal.
            12h.2 Decorative Metal Fencing & Gates                   145 lf  $             252.00 $              37,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System                8,514 sf  $                 5.40 $              46,000
            12i.2 Emergency Lighting                8,514 sf  $                 1.40 $              12,000
            12j New public address/emergency communication
            systems                               8,514 sf  $                 7.60 $              65,000
            12k Intrusion alarms                  8,514 sf  $                 1.80 $              15,000
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $              138,000 $                    184,000
            14b Learning Courts
            14b.2 New Learning Court                6,000 sf  $               23.00 $            138,000
           15 Exterior Play Spaces, Playfields & Hardcourts  $              822,000 $                 1,093,000
            15a Kindergarten Play Yard
            15a.1 New Rubberized Surface Play Area                2,925 sf  $               20.00 $              59,000
            15a.3 Shade Structure                 1,200 sf  $               90.00 $            108,000
            15b PE Play Yard & Hardcourts
            15a.1 New Rubberized Surface Play Area                3,600 sf  $               20.00 $              72,000
            15b.4 Shade Structure                 2,400 sf  $               90.00 $            216,000
            15b.7 Slurry Coat & Stripe Existing Hardcourts             41,750 sf  $                 3.00 $            125,000
            15b.8 Basketball Court/Sports Equipment                        1 ls  $       25,333.33 $              25,000
            15c Playfields
            15c.1 Repair Playfields             72,300 sf  $                 3.00 $            217,000
           16 Next Generation Classroom Flexibility (Furniture)  $              195,000 $                    195,000
            16a Flexible furniture (Per Classroom, Direct Cost)                     13 ea  $       15,000.00 $            195,000
           17 Technology Infrastructure                    $                       -  $                             -
            Not included in this Facilities Needs Assessment

          Total Construction/Project Cost (2016$)          $         15,858,000  $21,027,000








         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  506
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District