Page 531 - Facilities Master Plan 2016
P. 531

Lodi Unified School District                                            Lodi Unified School District
          Lawrence Elementary School                                              Lawrence Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Lawrence Elementary School               Project Cost Summary (2016$) - Lawrence Elementary School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          12 Safety, Security & Campus Control             $              819,000 $                 1,089,000  The following items are excluded from this budget:
            12b Safety improvements to and/or new parent/bus drop-off areas and parking  Utility hook-up fees & City connection fees.
            12b.5 New Drop-off Area                3,960 sf  $               18.00 $              71,000  Offsite work and traffic signals.
            12b.9 Repair existing Parking Lot             14,850 sf  $                 6.30 $              94,000  Land acquisition costs.
            12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000  Hazardous material surveys, abatement, and disposal.
            12e Safety locks at classroom doors                     30 ea  $             449.00 $              13,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000
            12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                   665 lf  $             252.00 $            168,000
            12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $              27,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System             21,936 sf  $                 5.40 $            118,000
            12i.2 Emergency Lighting             21,936 sf  $                 1.40 $              31,000
            12j New public address/emergency communication
            systems                            21,936 sf  $                 7.60 $            167,000
            12k Intrusion alarms               21,936 sf  $                 1.80 $              39,000
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $              278,000 $                    370,000
            14a Main Student Quad
            14a.2 New Main Student Quad                7,700 sf  $               21.85 $            168,000
            14b Learning Courts
            14b.2 New Learning Court                4,800 sf  $               23.00 $            110,000
           15 Exterior Play Spaces, Playfields & Hardcourts  $           1,038,000 $                 1,381,000
            15a Kindergarten Play Yard
            15a.1 New Rubberized Surface Play Area                3,000 sf  $               20.00 $              60,000
            15a.3 Shade Structure                 1,200 sf  $               90.00 $            108,000
            15b PE Play Yard & Hardcourts
            15a.1 New Rubberized Surface Play Area                3,000 sf  $               20.00 $              60,000
            15b.4 Shade Structure                 2,400 sf  $               90.00 $            216,000
            15b.5 Resurface & Repair Hardcourts             46,400 sf  $                 5.00 $            232,000
            15b.8 Basketball Court/Sports Equipment                        1 ls  $       25,333.33 $              25,000
            15c Playfields
            15c.1 Repair Playfields           112,200 sf  $                 3.00 $            337,000
           16 Next Generation Classroom Flexibility (Furniture)  $              345,000 $                    345,000
            16a Flexible furniture (Per Classroom, Direct Cost)                     23 ea  $       15,000.00 $            345,000
           17 Technology Infrastructure                    $                       -  $                             -
            Not included in this Facilities Needs Assessment

          Total Construction/Project Cost (2016$)          $         15,407,000  $20,377,000


         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  502
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District