Lodi Unified School District                                           Lodi Unified School District
          Lakewood Elementary School                                             Lakewood Elementary School
          Facilities Master Plan - Total Program Cost                            Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16  Opinion of Probable Cost                                     19-Apr-16
                         Project Cost Summary (2016$) - Lakewood Elementary School               Project Cost Summary (2016$) - Lakewood Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            4b.10 Sitework & Site Improvements                5,746 sf  $               38.00 $             218,000  11a.5 Sitework & Site Improvements                4,290 sf  $               38.00 $             163,000
           4d Student Collaboration Lab                                            11d Learning Center
            4d.1 New Student Collaboration Lab, 2 - Story                1,915 sf  $             426.60 $             817,000  11d.4 Reconfigure Learning Center                1,408 sf  $             237.00 $             334,000
            4d.2 Sitework & Site Improvements                   958 sf  $               38.00 $               36,000
                                                                                 12 Safety, Security & Campus Control             $             1,982,000 $                 2,636,000
          05 Maker Spaces & Science Labs                  $                622,000 $                    827,000  12a  Remaining asbestos removal             24,988 sf  $                 4.00 $             100,000
           5a ES Science / Creativity Labs                                         12b Safety improvements to and/or new parent/bus drop-off areas and parking
                                                                                   12b.1 New Parking Lot              47,850 sf  $               16.00 $             766,000
            5a.5 Reconfigure ES Science / Creativity Labs Building                 2,560 sf  $             243.00 $             622,000  12b.3 Entry Plaza                2,000 sf  $               26.00 $               52,000
                                                                                    12b.11 New concrete walkways                5,600 sf  $               15.00 $               84,000
                                                                                    12b.12 Repair concrete walkways             10,383 sf  $                 8.00 $               83,000
          06 Electives                                    $                         -  $                             -  12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $               40,000
           Not included in this Facilities Needs Assessment                        12e Safety locks at classroom doors                     30 ea  $             449.00 $               13,000
                                                                                   12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $               32,000
                                                                                   12g Marquee Sign                              1 ea  $       10,000.00 $               10,000
          07 Performing Arts Improvements                 $                938,000 $                 1,248,000  12h Fencing with controlled campus entrances
           7a Music Lab                                                             12h.2 Decorative Metal Fencing & Gates                1,468 lf  $             252.00 $             370,000
            7a.4 New Music Lab                    1,862 sf  $             484.92 $             903,000  2-story  12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $               27,000
            7a.5 Sitework & Site Improvements                   931 sf  $               38.00 $               35,000  12i Fire safety equipment, fire alarms and emergency lighting
                                                                                    12i.1 Fire Alarm System             24,988 sf  $                 5.40 $             135,000
                                                                                    12i.2 Emergency Lighting             24,988 sf  $                 1.40 $               35,000
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $             1,620,000 $                 2,155,000  12j New public address/emergency communication
           8a Elementary/Middle School multipurpose rooms                          systems                            24,988 sf  $                 7.60 $             190,000
            8a.2 Modernize Multipurpose Room                3,000 sf  $               99.00 $             297,000  12k Intrusion alarms             24,988 sf  $                 1.80 $               45,000
            8a.4 New Multipurpose Room                   875 sf  $             494.00 $             432,000
            8a.5 Sitework & Site Improvements                   875 sf  $               38.00 $               33,000
           8c Food service areas                                                 13 District Support Facilities                   $                         -  $                             -
            8c.3 Reconfigure Food Service                   280 sf  $             350.00 $               98,000  Not included in this Facilities Needs Assessment
            8c.4 New Food Service                 1,120 sf  $             584.00 $             654,000
            8c.5 New Kitchen Equipment                   280 sf  $               63.00 $               18,000
            8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $               45,000  14 Outdoor Learning Environments & Quads  $                277,000 $                    368,000
            8c.9 Sitework & Site Improvements                1,120 sf  $               38.00 $               43,000  14a Main Student Quad
                                                                                   14a.2 New Main Student Quad             10,000 sf  $               19.55 $             196,000
                                                                                   14b Learning Courts
          09 Physical Education Improvements              $             1,163,000 $                 1,547,000  14b.2 New Learning Court                3,500 sf  $               23.00 $               81,000
           9c PE/Fitness Labs
            9c.4 New PE/Fitness Labs                2,554 sf  $             436.32 $          1,114,000  2-story
            9c.5 Sitework & Site Improvements                1,277 sf  $               38.00 $               49,000  15 Exterior Play Spaces, Playfields & Hardcourts  $             1,768,000 $                 2,351,000
                                                                                   15a Kindergarten Play Yard
                                                                                    15a.1 New Rubberized Surface Play Area                1,800 sf  $               20.00 $               36,000
          10 Administration & Staff Support               $                977,000 $                 1,299,000  15a.3 Shade Structure                1,200 sf  $               90.00 $             108,000
           10a Expanded, reorganized or relocated administration                    15a.5 Resurface & Repair Hardcourts                4,950 sf  $                 5.00 $               25,000
           spaces                                                                   15a.6 New Hardcourts                 7,000 sf  $               11.00 $               77,000
            10a.3 Reconfigure Administration                2,250 sf  $             235.00 $             529,000  15b PE Play Yard & Hardcourts
           10b Staff Collaboration/Work Rooms                                       15a.1 New Rubberized Surface Play Area                4,000 sf  $               20.00 $               80,000
            10b.2 Modernize Staff Collaboration/Work Rooms                1,576 sf  $             118.00 $             186,000  15b.3 Relocate Elementary Play Apparatus                        1 ea  $       18,000.00 $               18,000
            10b.4 New Staff Collaboration/Work Rooms                   638 sf  $             392.00 $             250,000  2-story  15b.4 Shade Structure                2,400 sf  $               90.00 $             216,000
            10b.5 Sitework & Site Improvements                   319 sf  $               38.00 $               12,000  15b.5 Resurface & Repair Hardcourts             23,400 sf  $                 5.00 $             117,000
                                                                                    15b.6 New Hardcourts              57,600 sf  $               11.00 $             634,000
                                                                                    15b.8 Basketball Court/Sports Equipment                        1 ls  $       38,000.00 $               38,000
          11 Library & Student Support Services           $             2,239,000 $                 2,978,000  15c Playfields
           11a Elementary School Library/Innovation Lab                             15c.1 Repair Playfields           139,650 sf  $                 3.00 $             419,000
            11a.2 New Library/Innovation Lab Building                4,290 sf  $             406.00 $          1,742,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  498
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District