Page 522 - Facilities Master Plan 2016
P. 522

Lodi Unified School District                                            Lodi Unified School District
          Elkhorn School                                                          Heritage Primary Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                             Project Cost Summary (2016$) - Elkhorn School                     Project Cost Summary (2016$) - Heritage Primary Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
           17 Technology Infrastructure                    $                 64,000 $                      64,000  01 Modernize & Reconfigure Aging Classrooms  $           1,508,000 $                 2,006,000
             17c MDF and IDF data rooms with environmental control                 1b Replacement or repair of walls
            (direct cost only)                            2 ea  $       32,000.00 $              64,000  1b.1 Replace walls                 5,760 sf  $               39.50 $            228,000
                                                                                    1b.2 Repair walls                  14,400 sf  $               12.60 $            181,000
                                                                                   1d Replacement or repair of doors (other than safety locks
          Total Construction/Project Cost (2016$)          $         20,784,000  $27,602,000  @ classroom doors)
                                                                                    1d.1 Replace doors & hardware             20,160 sf  $               13.50 $            272,000
                                                                                   1e Replacement or repair of floors
          The following items are excluded from this budget:                        1e.1 Replace floors                   5,760 sf  $               14.40 $              83,000
           Utility hook-up fees & City connection fees.                             1e.2 Repair floors                 14,400 sf  $               10.80 $            156,000
           Offsite work and traffic signals.                                       1f Replacement or repair of ceilings
           Land acquisition costs.                                                  1f.1 Replace ceilings                 5,760 sf  $               27.00 $            156,000
           Hazardous material surveys, abatement, and disposal.                     1f.2 Repair ceilings               14,400 sf  $                 8.10 $            117,000
           Escalation (Costs are in 2016$ calculated to the end of the year).      1g Patch & Paint Interior/Exterior
                                                                                    1g.1 Patch & paint interior             20,160 sf  $                 3.10 $              62,000
                                                                                    1g.2 Patch & paint exterior             20,160 sf  $                 4.50 $              91,000
                                                                                   1m Patch Existing Roofing             26,966 sf  $                 6.00 $            162,000
                                                                                  02 Existing Building Systems & Toilets          $           1,154,000 $                 1,535,000
                                                                                   2a HVAC system upgrades             20,160 sf  $               29.00 $            585,000
                                                                                   2b Lighting upgrades - new interior lighting & controls             20,160 sf  $                 7.50 $            151,000  50% of cost
                                                                                   2c Electrical upgrades
                                                                                    2c.1 Upgrade electrical wiring & increase electrical
                                                                                    outlets                            20,160 sf  $                 4.50 $              91,000  50% of cost
                                                                                   2d Plumbing system upgrades             20,160 sf  $                 5.50 $            111,000  50% of cost
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.1 Modernize Existing Restroom                   856 sf  $               83.00 $              71,000
                                                                                   2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)             20,160 sf  $                 7.20 $            145,000
                                                                                  03 Site Utilities                               $              532,000 $                    708,000
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines           226,512 sf  $                 0.20 $              45,000  50% of cost
                                                                                   3b Updated sewer service lines           226,512 sf  $                 0.35 $              79,000  50% of cost
                                                                                   3c Updated water service lines           226,512 sf  $                 0.45 $            102,000  50% of cost
                                                                                   3d Updated electrical mains and distribution           226,512 sf  $                 0.90 $            204,000  50% of cost
                                                                                   3e Updated storm drainage system           226,512 sf  $                 0.45 $            102,000  50% of cost
                                                                                  04 Classrooms New Construction                  $         10,257,000 $              13,642,000
                                                                                   4b New Construction - Classrooms
                                                                                    4b.1 Remove Portable Classrooms                        9 ea  $       11,000.00 $              99,000
                                                                                    4b.5 New Elementary Classroom Building (2-story)             19,790 sf  $             449.00 $         8,886,000
                                                                                    4b.10 Sitework & Site Improvements                9,895 sf  $               38.00 $            376,000
                                                                                   4d Student Collaboration Lab
                                                                                    4d.1 New Student Collaboration Lab, 2- Story                1,915 sf  $             449.00 $            860,000
                                                                                    4d.2 Sitework & Site Improvements             957.60 sf  $               38.00 $              36,000


         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  493
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   517   518   519   520   521   522   523   524   525   526   527