Page 526 - Facilities Master Plan 2016
P. 526

Lodi Unified School District                                           Lodi Unified School District
          Houston Elementary School                                              Lakewood Elementary School
          Facilities Master Plan - Total Program Cost                            Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                          Project Cost Summary (2016$) - Houston Elementary School               Project Cost Summary (2016$) - Lakewood Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item   Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          The following items are excluded from this budget:                     01 Modernize & Reconfigure Aging Classrooms      $             2,112,000 $                 2,809,000
           Utility hook-up fees & City connection fees.                            1b Replacement or repair of walls
           Offsite work and traffic signals.                                       1b.2 Repair walls                  13,830 sf  $               12.60 $             174,000
           Land acquisition costs.                                                 1c Replacement or repair of windows
           Hazardous material surveys, abatement, and disposal.                    1c.1 Replace windows               13,830 sf  $               18.00 $             249,000
           Escalation (Costs are in 2016$ calculated to the end of the year).      1d Replacement or repair of doors (other than safety locks
                                                                                   @ classroom doors)
                                                                                   1d.1 Replace doors & hardware             13,830 sf  $               13.50 $             187,000
                                                                                   1e Replacement or repair of floors
                                                                                   1e.2 Repair floors                 13,830 sf  $               10.80 $             149,000
                                                                                   1f Replacement or repair of ceilings
                                                                                   1f.1 Replace ceilings              13,830 sf  $               27.00 $             373,000
                                                                                   1g Patch & Paint Interior/Exterior
                                                                                   1g.1 Patch & paint interior             13,830 sf  $                 3.10 $               43,000
                                                                                   1g.2 Patch & paint exterior             13,830 sf  $                 4.50 $               62,000
                                                                                   1o Replace Existing Roofing             35,371 sf  $               20.93 $             740,000
                                                                                   1p Repair Existing Covered Walkways / Hallways             10,383 sf  $               13.00 $             135,000
                                                                                 02 Existing Building Systems & Toilets           $             1,315,000 $                 1,749,000
                                                                                   2a HVAC system upgrades             13,830 sf  $               29.00 $             401,000
                                                                                   2b Lighting upgrades - new interior lighting & controls             13,830 sf  $               15.00 $             207,000
                                                                                   2c Electrical upgrades
                                                                                   2c.1 Upgrade electrical wiring & increase electrical
                                                                                   outlets                            13,830 sf  $                 9.00 $             124,000
                                                                                   2d Plumbing system upgrades             13,830 sf  $               11.00 $             152,000
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                   2e.2 Reconfigure Existing Restroom                1,492 sf  $             222.00 $             331,000
                                                                                   2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)             13,830 sf  $                 7.20 $             100,000
                                                                                 03 Site Utilities                                $             1,217,000 $                 1,619,000
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines           453,024 sf  $                 0.20 $               91,000
                                                                                   3b Updated sewer service lines           453,024 sf  $                 0.42 $             190,000
                                                                                   3c Updated water service lines           453,024 sf  $                 0.54 $             245,000
                                                                                   3d Updated electrical mains and distribution           453,024 sf  $                 0.72 $             326,000
                                                                                   3e Updated storm drainage system           453,024 sf  $                 0.45 $             204,000
                                                                                   3f Electrical Capacity Upgrades                        1 ls  $     161,000.00 $             161,000
                                                                                 04 Classrooms New Construction                   $             8,836,000 $              11,752,000
                                                                                   4a New Construction - Pre-School, DK & Kindergarten
                                                                                   4a.2 New Pre-School, DK & Kindergarten Building                5,940 sf  $             395.00 $          2,346,000
                                                                                   4a.4 Sitework & Site Improvements                5,940 sf  $               38.00 $             226,000
                                                                                   4b New Construction - Classrooms
                                                                                   4b.1 Remove Portable Classrooms                        3 ea  $       11,000.00 $               33,000
                                                                                   4b.5 New Elementary Classroom Building (2-story)             11,491 sf  $             449.00 $          5,160,000

         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  497
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   521   522   523   524   525   526   527   528   529   530   531