Page 521 - Facilities Master Plan 2016
P. 521

Lodi Unified School District                                            Lodi Unified School District
          Elkhorn School                                                          Elkhorn School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                             Project Cost Summary (2016$) - Elkhorn School                           Project Cost Summary (2016$) - Elkhorn School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          05 Maker Spaces & Science Labs                   $           2,614,000 $                 3,477,000  12 Safety, Security & Campus Control  $              798,000 $                 1,061,000
            5a ES Science / Creativity Labs                                        12a  Remaining asbestos removal             10,350 sf  $                 4.00 $              41,000
            5a.6 New ES Science / Creativity Labs Building                 1,540 sf  $             440.00 $            678,000  12b Safety improvements to and/or new parent/bus drop-off areas and parking
            5a.7 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000  12b.3 Entry Plaza                2,400 sf  $               26.00 $              62,000
            5b MS / HS Science Labs                                                 12b.6 Resurface and Repair Access Road                6,500 sf  $                 8.10 $              53,000
            5b.1 New MS/HS  Science Labs Building                 3,724 sf  $             484.92 $         1,806,000  2-story building  12b.9 Repair existing Parking Lot             26,250 sf  $                 6.30 $            165,000
            5b.2 Sitework & Site Improvements                1,862 sf  $               38.00 $              71,000  12b.11 New concrete walkways                2,600 sf  $               15.00 $              39,000
                                                                                   12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
                                                                                   12e Safety locks at classroom doors                     10 ea  $             449.00 $                 4,000
          06 Electives                                     $           1,732,000 $                 2,304,000  12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
            6a MS/HS Electives                                                     12g Marquee Sign                               1 ea  $       10,000.00 $              10,000
            6a.6 New MS/HS Electives Building                 3,724 sf  $             446.04 $         1,661,000  2-story building  12h Fencing with controlled campus entrances
            6a.7 Sitework & Site Improvements                1,862 sf  $               38.00 $              71,000  12h.2 Decorative Metal Fencing & Gates                   515 lf  $             252.00 $            130,000
                                                                                    12h.3 Rolling Decorative Metal Gate                        2 ea  $       27,000.00 $              54,000
                                                                                   12i Fire safety equipment, fire alarms and emergency lighting
          07 Performing Arts Improvements                  $              750,000 $                    998,000  12i.1 Fire Alarm System             10,350 sf  $                 5.40 $              56,000
            7a Music Lab                                                            12i.2 Emergency Lighting             10,350 sf  $                 1.40 $              14,000
            7a.4 New Music Lab                    1,540 sf  $             449.00 $            691,000  12j New public address/emergency communication
            7a.5 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000  systems              10,350 sf  $                 7.60 $              79,000
                                                                                   12k Intrusion alarms                10,350 sf  $                 1.80 $              19,000
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $           2,971,000 $                 3,951,000
            8a Elementary/Middle School multipurpose rooms                        13 District Support Facilities                  $                       -  $                             -
            8a.4 New Multipurpose Room                5,500 sf  $             494.00 $         2,717,000  Not included in this Facilities Needs Assessment
            8a.5 Sitework & Site Improvements                5,500 sf  $               38.00 $            209,000
            8c Food service areas
            8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $              45,000  14 Outdoor Learning Environments & Quads  $              392,000 $                    521,000
                                                                                   14a Main Student Quad
                                                                                    14a.2 New Main Student Quad             16,000 sf  $               17.25 $            276,000
          09 Physical Education Improvements               $              933,000 $                 1,241,000  14b Learning Courts
            9c PE/Fitness Labs                                                      14b.2 New Learning Court                5,600 sf  $               20.70 $            116,000
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00 $            853,000
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000
                                                                                  15 Exterior Play Spaces, Playfields & Hardcourts  $           1,343,000 $                 1,786,000
                                                                                   15b PE Play Yard & Hardcourts
          10 Administration & Staff Support                $           1,084,000 $                 1,442,000  15a.1 New Rubberized Surface Play Area                2,400 sf  $               20.00 $              48,000
            10a Expanded, reorganized or relocated administration                   15b.3 Relocate Elementary Play Apparatus                        1 ea  $       18,000.00 $              18,000
            spaces                                                                  15b.4 Shade Structure                 2,400 sf  $               90.00 $            216,000
            10a.3 Reconfigure Administration                1,920 sf  $             235.00 $            451,000  15b.6 New Hardcourts             55,800 sf  $               11.00 $            614,000
            10b Staff Collaboration/Work Rooms                                      15b.8 Basketball Court/Sports Equipment                        1 ls  $       38,000.00 $              38,000
            10b.3 Reconfigure Staff Collaboration/Work Rooms                1,440 sf  $             235.00 $            338,000  15c Playfields
            10b.4 New Staff Collaboration/Work Rooms                   665 sf  $             423.36 $            282,000  15c.1 Repair Playfields           120,000 sf  $                 3.00 $            360,000
            10b.5 Sitework & Site Improvements                   333 sf  $               38.00 $              13,000  15d Baseball/Softball Fields
                                                                                    15d.3 Pitching mound/bases, per field                        1 ea  $       22,000.00 $              22,000
                                                                                    15d.4 Backstops, per field                        1 ea  $       27,000.00 $              27,000
          11 Library & Student Support Services            $           1,583,000 $                 2,105,000
            11b Middle School/High School Library/Innovation Lab                    Not included in this Facilities Needs Assessment
            11b.2 New Library/Innovation Lab                1,320 sf  $             406.00 $            536,000
            11b.4 Reconfigure Library/Innovation Lab                3,150 sf  $             244.00 $            769,000
            11b.5 Sitework & Site Improvements                1,320 sf  $               38.00 $              50,000  16 Next Generation Classroom Flexibility (Furniture)  $                 60,000 $                      60,000
            11d Learning Center                                                    16a Flexible furniture (Per Classroom, Direct Cost)                        4 ea  $       15,000.00 $              60,000
            11d.4 Reconfigure Learning Center                   960 sf  $             237.00 $            228,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  492