Page 517 - Facilities Master Plan 2016
P. 517

Lodi Unified School District                                            Lodi Unified School District
          Creekside Elementary School                                             Creekside Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Creekside Elementary School              Project Cost Summary (2016$) - Creekside Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            4b.10 Sitework & Site Improvements                9,504 sf  $               38.00 $            361,000
            4d Student Collaboration Lab                                          12 Safety, Security & Campus Control            $           1,888,000 $                 2,511,000
            4d.1 New Student Collaboration Lab, 1- Story                1,584 sf  $             395.00 $            626,000  12b Safety improvements to and/or new parent/bus drop-off areas and parking
            4d.2 Sitework & Site Improvements                1,584 sf  $               38.00 $              60,000  12b.1 New Parking Lot             60,650 sf  $               16.00 $            970,000
                                                                                    12b.3 Entry Plaza                     6,000 sf  $               26.00 $            156,000
                                                                                    12b.11 New concrete walkways                5,800 sf  $               15.00 $              87,000
          05 Maker Spaces & Science Labs                   $           1,472,000 $                 1,958,000  12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
            5a ES Science / Creativity Labs                                        12e Safety locks at classroom doors                     30 ea  $             449.00 $              13,000
            5a.6 New ES Science / Creativity Labs Building                 3,080 sf  $             440.00 $         1,355,000  12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
            5a.7 Sitework & Site Improvements                3,080 sf  $               38.00 $            117,000  12g Marquee Sign                        1 ea  $       10,000.00 $              10,000
                                                                                   12h Fencing with controlled campus entrances
                                                                                    12h.2 Decorative Metal Fencing & Gates                   785 lf  $             252.00 $            198,000
          06 Electives                                     $                       -  $                             -  12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $              27,000
            Not included in this Facilities Needs Assessment                       12i Fire safety equipment, fire alarms and emergency lighting
                                                                                    12i.1 Fire Alarm System             21,926 sf  $                 5.40 $            118,000
                                                                                    12i.2 Emergency Lighting             21,926 sf  $                 1.40 $              31,000
          07 Performing Arts Improvements                  $              750,000 $                    998,000  12j New public address/emergency communication
            7a Music Lab                                                           systems                             21,926 sf  $                 7.60 $            167,000
            7a.4 New Music Lab                    1,540 sf  $             449.00 $            691,000  12k Intrusion alarms             21,926 sf  $                 1.80 $              39,000
            7a.5 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000
                                                                                  13 District Support Facilities                  $                       -  $                             -
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $           1,937,000 $                 2,576,000  Not included in this Facilities Needs Assessment
            8a Elementary/Middle School multipurpose rooms
            8a.2 Modernize Multipurpose Room                3,250 sf  $               99.00 $            322,000
            8a.4 New Multipurpose Room                2,600 sf  $             494.00 $         1,284,000  14 Outdoor Learning Environments & Quads  $              394,000 $                    524,000
            8a.5 Sitework & Site Improvements                2,600 sf  $               38.00 $              99,000  14a Main Student Quad
            8c Food service areas                                                   14a.2 New Main Student Quad             16,025 sf  $               17.25 $            276,000
            8c.2 Modernize Food Service                1,071 sf  $             175.00 $            187,000  14b Learning Courts
            8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $              45,000  14b.2 New Learning Court                5,400 sf  $               21.85 $            118,000
          09 Physical Education Improvements               $              933,000 $                 1,241,000  15 Exterior Play Spaces, Playfields & Hardcourts  $           1,431,000 $                 1,903,000
            9c PE/Fitness Labs                                                     15a Kindergarten Play Yard
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00 $            853,000  15a.1 New Rubberized Surface Play Area                2,250 sf  $               20.00 $              45,000
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000  15a.3 Shade Structure                1,200 sf  $               90.00 $            108,000
                                                                                   15b PE Play Yard & Hardcourts
                                                                                    15a.1 New Rubberized Surface Play Area                9,425 sf  $               20.00 $            189,000
          10 Administration & Staff Support                $              432,000 $                    575,000  15b.2 Elementary Play Apparatus                        1 ea  $       63,000.00 $              63,000
            10a Expanded, reorganized or relocated administration                   15b.4 Shade Structure                 2,400 sf  $               90.00 $            216,000
            spaces                                                                  15b.5 Resurface & Repair Hardcourts             48,575 sf  $                 5.00 $            243,000
            10a.2 Modernize Administration                2,145 sf  $             118.00 $            253,000  15b.8 Basketball Court/Sports Equipment                        1 ls  $       25,333.33 $              25,000
            10b Staff Collaboration/Work Rooms                                     15c Playfields
            10b.2 Modernize Staff Collaboration/Work Rooms                   560 sf  $             118.00 $              66,000  15c.1 Repair Playfields           180,825 sf  $                 3.00 $            542,000
            10b.3 Reconfigure Staff Collaboration/Work Rooms                   480 sf  $             235.00 $            113,000
                                                                                  16 Next Generation Classroom Flexibility (Furniture)  $              270,000 $                    270,000
          11 Library & Student Support Services            $           1,173,000 $                 1,560,000  16a Flexible furniture (Per Classroom, Direct Cost)                     18 ea  $       15,000.00 $            270,000
            11a Elementary School Library/Innovation Lab
            11a.4 Reconfigure Library/Innovation Lab Building                3,100 sf  $             244.00 $            756,000
            11d Learning Center                                                   17 Technology Infrastructure                    $                       -  $                             -
            11d.4 Reconfigure Learning Center                1,760 sf  $             237.00 $            417,000  Not included in this Facilities Needs Assessment
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  488
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District