Page 515 - Facilities Master Plan 2016
P. 515

Lodi Unified School District                                            Lodi Unified School District
          Clairmont Elementary School                                             Clairmont Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Clairmont Elementary School              Project Cost Summary (2016$) - Clairmont Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            4b.4 New Elementary Classroom Building (1-story)                4,224 sf  $             404.00 $         1,706,000  12 Safety, Security & Campus Control  $           1,149,000 $                 1,528,000
            4b.10 Sitework & Site Improvements                4,224 sf  $               38.00 $            161,000  12b Safety improvements to and/or new parent/bus drop-off areas and parking
            4d Student Collaboration Lab                                            12b.1 New Parking Lot              10,000 sf  $               16.00 $            160,000
            4d.1 New Student Collaboration Lab, 1- Story                1,056 sf  $             395.00 $            417,000  12b.3 Entry Plaza                2,400 sf  $               26.00 $              62,000
            4d.2 Sitework & Site Improvements                1,056 sf  $               38.00 $              40,000  12b.9 Repair existing Parking Lot             25,200 sf  $                 6.30 $            159,000
                                                                                    12b.12 Repair concrete walkways                4,500 sf  $                 8.00 $              36,000
                                                                                   12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
          05 Maker Spaces & Science Labs                   $           1,472,000 $                 1,958,000  12e Safety locks at classroom doors                     25 ea  $             449.00 $              11,000
            5a ES Science / Creativity Labs                                        12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
            5a.6 New ES Science / Creativity Labs Building                 3,080 sf  $             440.00 $         1,355,000  12g Marquee Sign                        1 ea  $       10,000.00 $              10,000
            5a.7 Sitework & Site Improvements                3,080 sf  $               38.00 $            117,000  12h Fencing with controlled campus entrances
                                                                                    12h.1 Chain Link Perimeter Fencing                   290 lf  $               99.00 $              29,000
                                                                                    12h.2 Decorative Metal Fencing & Gates                   370 lf  $             252.00 $              93,000
          06 Electives                                     $                       -  $                             -  12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $              27,000
            Not included in this Facilities Needs Assessment                        12h.4 Rolling Chain Link Gate                        1 ea  $       25,200.00 $              25,000
                                                                                   12i Fire safety equipment, fire alarms and emergency lighting
                                                                                    12i.1 Fire Alarm System             28,680 sf  $                 5.40 $            155,000
          07 Performing Arts Improvements                  $              750,000 $                    998,000  12i.2 Emergency Lighting             28,680 sf  $                 1.40 $              40,000
            7a Music Lab                                                           12j New public address/emergency communication
            7a.4 New Music Lab                    1,540 sf  $             449.00 $            691,000  systems              28,680 sf  $                 7.60 $            218,000
            7a.5 Sitework & Site Improvements                1,540 sf  $               38.00 $              59,000  12k Intrusion alarms             28,680 sf  $                 1.80 $              52,000
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $           1,173,000 $                 1,560,000  13 District Support Facilities  $                       -  $                             -
            8a Elementary/Middle School multipurpose rooms                         Not included in this Facilities Needs Assessment
            8a.2 Modernize Multipurpose Room                3,250 sf  $               99.00 $            322,000
            8a.4 New Multipurpose Room                1,250 sf  $             494.00 $            618,000
            8a.5 Sitework & Site Improvements                1,250 sf  $               38.00 $              48,000  14 Outdoor Learning Environments & Quads  $              149,000 $                    198,000
            8c Food service areas                                                  14b Learning Courts
            8c.2 Modernize Food Service                   800 sf  $             175.00 $            140,000  14b.2 New Learning Court                7,200 sf  $               20.70 $            149,000
            8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $              45,000
                                                                                  15 Exterior Play Spaces, Playfields & Hardcourts  $              934,000 $                 1,242,000
          09 Physical Education Improvements               $              933,000 $                 1,241,000  15a Kindergarten Play Yard
            9c PE/Fitness Labs                                                      15a.1 New Rubberized Surface Play Area                1,200 sf  $               20.00 $              24,000
            9c.4 New PE/Fitness Labs                2,112 sf  $             404.00 $            853,000  15a.3 Shade Structure                1,200 sf  $               90.00 $            108,000
            9c.5 Sitework & Site Improvements                2,112 sf  $               38.00 $              80,000  15a.6 New Hardcourts                3,200 sf  $                 5.50 $              18,000
                                                                                   15b PE Play Yard & Hardcourts
                                                                                    15a.1 New Rubberized Surface Play Area                2,400 sf  $               20.00 $              48,000
          10 Administration & Staff Support                $              472,000 $                    628,000  15b.4 Shade Structure                2,400 sf  $               90.00 $            216,000
            10a Expanded, reorganized or relocated administration                   15b.5 Resurface & Repair Hardcourts             60,800 sf  $                 5.00 $            304,000
            spaces                                                                 15c Playfields
            10a.2 Modernize Administration                2,900 sf  $             118.00 $            342,000  15c.1 Repair Playfields             72,000 sf  $                 3.00 $            216,000
            10b Staff Collaboration/Work Rooms
            10b.2 Modernize Staff Collaboration/Work Rooms                1,100 sf  $             118.00 $            130,000
                                                                                  16 Next Generation Classroom Flexibility (Furniture)  $              240,000 $                    240,000
                                                                                   16a Flexible furniture (Per Classroom, Direct Cost)                     16 ea  $       15,000.00 $            240,000
          11 Library & Student Support Services            $           1,281,000 $                 1,704,000
            11a Elementary School Library/Innovation Lab
            11a.4 Reconfigure Library/Innovation Lab Building                3,500 sf  $             244.00 $            854,000  17 Technology Infrastructure  $                       -  $                             -
            11d Learning Center                                                    Not included in this Facilities Needs Assessment
            11d.4 Reconfigure Learning Center                1,800 sf  $             237.00 $            427,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  486
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District