Page 524 - Facilities Master Plan 2016
P. 524

Lodi Unified School District                                            Lodi Unified School District
          Heritage Primary Elementary School                                      Houston Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                       Project Cost Summary (2016$) - Heritage Primary Elementary School         Project Cost Summary (2016$) - Houston Elementary School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
           17 Technology Infrastructure                    $                 32,000 $                      32,000  01 Modernize & Reconfigure Aging Classrooms  $           1,570,000 $                 2,088,000
             17c MDF and IDF data rooms with environmental control                 1b Replacement or repair of walls
            (direct cost only)                            1 ea  $       32,000.00 $              32,000  1b.2 Repair walls             10,740 sf  $               12.60 $            135,000
                                                                                   1c Replacement or repair of windows
                                                                                    1c.1 Replace windows               10,740 sf  $               18.00 $            193,000
          Total Construction/Project Cost (2016$)          $         23,179,000  $30,736,000  1d Replacement or repair of doors (other than safety locks
                                                                                   @ classroom doors)
                                                                                    1d.1 Replace doors & hardware             10,740 sf  $               13.50 $            145,000
          The following items are excluded from this budget:                       1e Replacement or repair of floors
           Utility hook-up fees & City connection fees.                             1e.2 Repair floors                 10,740 sf  $               10.80 $            116,000
           Offsite work and traffic signals.                                       1f Replacement or repair of ceilings
           Land acquisition costs.                                                  1f.2 Repair ceilings               10,740 sf  $                 8.10 $              87,000
           Hazardous material surveys, abatement, and disposal.                    1g Patch & Paint Interior/Exterior
           Escalation (Costs are in 2016$ calculated to the end of the year).       1g.1 Patch & paint interior             10,740 sf  $                 3.10 $              33,000
                                                                                    1g.2 Patch & paint exterior             10,740 sf  $                 4.50 $              48,000
                                                                                   1o Replace Existing Roofing             34,450 sf  $               20.93 $            721,000
                                                                                   1p Repair Existing Covered Walkways / Hallways                7,050 sf  $               13.00 $              92,000
                                                                                  02 Existing Building Systems & Toilets          $           1,094,000 $                 1,455,000
                                                                                   2a HVAC system upgrades             10,740 sf  $               29.00 $            311,000
                                                                                   2b Lighting upgrades - new interior lighting & controls             10,740 sf  $               15.00 $            161,000
                                                                                   2c Electrical upgrades
                                                                                    2c.1 Upgrade electrical wiring & increase electrical
                                                                                    outlets                            10,740 sf  $                 9.00 $              97,000
                                                                                   2d Plumbing system upgrades             10,740 sf  $               11.00 $            118,000
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.2 Reconfigure Existing Restroom                1,485 sf  $             222.00 $            330,000
                                                                                   2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)             10,740 sf  $                 7.20 $              77,000
                                                                                  03 Site Utilities                               $              993,000 $                 1,321,000
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines           373,309 sf  $                 0.20 $              75,000  50% of cost
                                                                                   3b Updated sewer service lines           373,309 sf  $                 0.35 $            131,000  50% of cost
                                                                                   3c Updated water service lines           373,309 sf  $                 0.45 $            168,000  50% of cost
                                                                                   3d Updated electrical mains and distribution           373,309 sf  $                 0.90 $            336,000  50% of cost
                                                                                   3e Updated storm drainage system           373,309 sf  $                 0.45 $            168,000  50% of cost
                                                                                   3f Electrical Capacity Upgrades                        1 ls  $     115,000.00 $            115,000  50% of cost
                                                                                  04 Classrooms New Construction                  $              296,000 $                    394,000
                                                                                   4a New Construction - Pre-School, DK & Kindergarten
                                                                                    4a.2 New Pre-School, DK & Kindergarten Building                   480 sf  $             395.00 $            190,000
                                                                                    4a.4 Sitework & Site Improvements                   480 sf  $               38.00 $              18,000
                                                                                   4b New Construction - Classrooms
                                                                                    4b.1 Remove Portable Classrooms                        8 ea  $       11,000.00 $              88,000


         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  495
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District