Page 590 - Facilities Master Plan 2016
P. 590

Lodi Unified School District                                            Lodi Unified School District
          Plaza Robles High School                                                Turner Academy at Tokay Colony
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                           Project Cost Summary (2016$) - Plaza Robles High School             Project Cost Summary (2016$) - Turner Academy at Tokay Colony
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System             18,470 sf  $                 5.40 $            100,000  01 Modernize & Reconfigure Aging Classrooms  $              474,000 $                    630,000
            12i.2 Emergency Lighting             18,470 sf  $                 1.40 $              26,000  1b Replacement or repair of walls
            12j New public address/emergency communication                          1b.2 Repair walls                     3,840 sf  $               12.60 $              48,000
            systems                            18,470 sf  $                 7.60 $            140,000  1c Replacement or repair of windows
            12k Intrusion alarms               18,470 sf  $                 1.80 $              33,000  1c.1 Replace windows                3,840 sf  $               18.00 $              69,000
                                                                                   1d Replacement or repair of doors (other than safety locks
                                                                                   @ classroom doors)
          13 District Support Facilities                   $                       -  $                             -  1d.1 Replace doors & hardware                3,840 sf  $               13.50 $              52,000
            Not included in this Facilities Needs Assessment                       1e Replacement or repair of floors
                                                                                    1e.2 Repair floors                    3,840 sf  $               10.80 $              41,000
                                                                                   1f Replacement or repair of ceilings
          14 Outdoor Learning Environments & Quads         $              124,000 $                    165,000  1f.2 Repair ceilings                3,840 sf  $                 8.10 $              31,000
            14b Learning Courts                                                    1g Patch & Paint Interior/Exterior
            14b.2 New Learning Court                5,400 sf  $               23.00 $            124,000  1g.1 Patch & paint interior                3,840 sf  $                 3.10 $              12,000
                                                                                    1g.2 Patch & paint exterior                3,840 sf  $                 4.50 $              17,000
                                                                                   1o Replace Existing Roofing                9,744 sf  $               20.93 $            204,000
           15 Exterior Play Spaces, Playfields & Hardcourts  $              186,000 $                    247,000
            15b PE Play Yard & Hardcourts
            15b.6 New Hardcourts               10,500 sf  $               11.00 $            116,000  02 Existing Building Systems & Toilets  $              322,000 $                    428,000
            15b.8 Basketball Court/Sports Equipment                        1 ls  $       12,666.67 $              13,000  2a HVAC system upgrades                3,840 sf  $               29.00 $            111,000
            15c Playfields
            15c.1 Repair Playfields             18,950 sf  $                 3.00 $              57,000  2b Lighting upgrades - new interior lighting & controls                3,840 sf  $               15.00 $              58,000
                                                                                   2c Electrical upgrades
                                                                                    2c.1 Upgrade electrical wiring & increase electrical
           16 Next Generation Classroom Flexibility (Furniture)  $              135,000 $                    135,000  outlets                3,840 sf  $                 9.00 $              35,000
            16a Flexible furniture (Per Classroom, Direct Cost)                        9 ea  $       15,000.00 $            135,000  2d Plumbing system upgrades                3,840 sf  $               11.00 $              42,000
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.1 Modernize Existing Restroom                   576 sf  $               83.00 $              48,000
           17 Technology Infrastructure                    $                       -  $                             -
            Not included in this Facilities Needs Assessment                       2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)                3,840 sf  $                 7.20 $              28,000
          Total Construction/Project Cost (2016$)          $           5,959,000  $7,880,000
                                                                                  03 Site Utilities                               $              588,000 $                    782,000
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines           423,403 sf  $                 0.16 $              68,000
          The following items are excluded from this budget:
           Utility hook-up fees & City connection fees.                            3b Updated sewer service lines           423,403 sf  $                 0.28 $            119,000
           Offsite work and traffic signals.                                       3c Updated water service lines           423,403 sf  $                 0.36 $            152,000
                                                                                                             423,403 sf
                                                                                                                    $
                                                                                                                        0.45 $
                                                                                                                              191,000
                                                                                   3d Updated electrical mains and distribution

           Land acquisition costs.                                                 3f Electrical Capacity Upgrades                        1 ls  $       57,500.00 $              58,000
           Hazardous material surveys, abatement, and disposal.
           Escalation (Costs are in 2016$ calculated to the end of the year).
                                                                                  04 Classrooms New Construction                  $           1,411,000 $                 1,877,000
                                                                                   4b New Construction - Classrooms
                                                                                    4b.1 Remove Portable Classrooms                        1 ea  $       11,000.00 $              11,000
                                                                                    4b.4 New Elementary Classroom Building (1-story)                3,168 sf  $             404.00 $         1,280,000
                                                                                    4b.10 Sitework & Site Improvements                3,168 sf  $               38.00 $            120,000
                                                                                  05 Maker Spaces & Science Labs                  $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  561
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   585   586   587   588   589   590   591   592   593   594   595