Page 586 - Facilities Master Plan 2016
P. 586

Lodi Unified School District                                            Lodi Unified School District
          Henderson Community Day Middle School                                   Liberty High School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                      Project Cost Summary (2016$) - Henderson Community Day Middle School         Project Cost Summary (2016$) - Liberty High School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          The following items are excluded from this budget:                      01 Modernize & Reconfigure Aging Classrooms     $              615,000 $                    818,000
           Utility hook-up fees & City connection fees.                            1b Replacement or repair of walls
           Offsite work and traffic signals.                                        1b.1 Replace walls                    1,846 sf  $               39.50 $              73,000
           Land acquisition costs.                                                  1b.2 Repair walls                     2,128 sf  $               12.60 $              27,000
           Hazardous material surveys, abatement, and disposal.                    1c Replacement or repair of windows
           Escalation (Costs are in 2016$ calculated to the end of the year).       1c.1 Replace windows                  3,974 sf  $               18.00 $              72,000
                                                                                   1d Replacement or repair of doors (other than safety locks
                                                                                   @ classroom doors)
                                                                                    1d.1 Replace doors & hardware                3,974 sf  $               13.50 $              54,000
                                                                                   1e Replacement or repair of floors
                                                                                    1e.1 Replace floors                   3,974 sf  $               14.40 $              57,000
                                                                                   1f Replacement or repair of ceilings
                                                                                    1f.1 Replace ceilings                 3,974 sf  $               27.00 $            107,000
                                                                                   1g Patch & Paint Interior/Exterior
                                                                                    1g.1 Patch & paint interior                3,974 sf  $                 3.10 $              12,000
                                                                                    1g.2 Patch & paint exterior                3,974 sf  $                 4.50 $              18,000
                                                                                   1o Replace Existing Roofing                9,294 sf  $               20.93 $            195,000
                                                                                  02 Existing Building Systems & Toilets          $              327,000 $                    435,000
                                                                                   2a HVAC system upgrades                3,974 sf  $               29.00 $            115,000
                                                                                   2b Lighting upgrades - new interior lighting & controls                3,974 sf  $               15.00 $              60,000
                                                                                   2c Electrical upgrades
                                                                                    2c.1 Upgrade electrical wiring & increase electrical
                                                                                    outlets                               3,974 sf  $                 9.00 $              36,000
                                                                                   2d Plumbing system upgrades                3,974 sf  $               11.00 $              44,000
                                                                                   2e Replace aging plumbing, upgrade and/or expand
                                                                                   restroom facilities
                                                                                    2e.1 Modernize Existing Restroom                   524 sf  $               83.00 $              43,000
                                                                                   2f Energy-efficient building systems and controls (EMS
                                                                                   system, per sf of Bldg)                3,974 sf  $                 7.20 $              29,000
                                                                                  03 Site Utilities                               $              211,000 $                    281,000
                                                                                   (For entire campus and site)
                                                                                   3a Updated gas service lines             43,560 sf  $                 0.30 $              13,000
                                                                                   3b Updated sewer service lines             43,560 sf  $                 0.53 $              23,000
                                                                                   3c Updated water service lines             43,560 sf  $                 0.68 $              29,000
                                                                                   3d Updated electrical mains and distribution             43,560 sf  $                 1.35 $              59,000
                                                                                   3e Updated storm drainage system             43,560 sf  $                 0.68 $              29,000
                                                                                   3f Electrical Capacity Upgrades                        1 ls  $       57,500.00 $              58,000
                                                                                  04 Classrooms New Construction                  $                       -  $                             -
                                                                                   Not included in this Facilities Needs Assessment
                                                                                  05 Maker Spaces & Science Labs                  $              176,000 $                    234,000
                                                                                   5b MS / HS Science Labs
                                                                                    5b.3 Reconfigure MS / HS Science Labs Building                    724 sf  $             243.00 $            176,000



         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  557
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District