Lodi Unified School District                                            Lodi Unified School District
          Ronald McNair High School                                               Ronald McNair High School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                          Project Cost Summary (2016$) - Ronald McNair High School               Project Cost Summary (2016$) - Ronald McNair High School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          01 Modernize & Reconfigure Aging Classrooms      $              406,000 $                    540,000  07 Performing Arts Improvements  $              912,000 $                 1,213,000
            1b Replacement or repair of walls                                      7a Music Lab
            1b.1 Replace walls                    2,880 sf  $               39.50 $            114,000  7a.4 New Music Lab                2,031 sf  $             449.00 $            912,000
            1c Replacement or repair of windows                                     7a.5 Sitework & Site Improvements  sf  $               38.00 $                     -
            1c.1 Replace windows                  2,880 sf  $               18.00 $              52,000
            1d Replacement or repair of doors (other than safety locks
            @ classroom doors)                                                    08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                       -  $                             -
            1d.1 Replace doors & hardware                2,880 sf  $               13.50 $              39,000  Not included in this Facilities Needs Assessment
            1e Replacement or repair of floors
            1e.1 Replace floors                   2,880 sf  $               14.40 $              41,000
            1f Replacement or repair of ceilings                                  09 Physical Education Improvements              $                       -  $                             -
            1f.1 Replace ceilings                 2,880 sf  $               27.00 $              78,000  Not included in this Facilities Needs Assessment
            1g Patch & Paint Interior/Exterior
            1g.1 Patch & paint interior                2,880 sf  $                 3.10 $                 9,000
            1g.2 Patch & paint exterior                2,880 sf  $                 4.50 $              13,000  10 Administration & Staff Support  $                       -  $                             -
            1o Replace Existing Roofing                2,880 sf  $               20.93 $              60,000  Not included in this Facilities Needs Assessment
          02 Existing Building Systems & Toilets           $              206,000 $                    274,000  11 Library & Student Support Services  $                       -  $                             -
            2a HVAC system upgrades                2,880 sf  $               29.00 $              84,000  Not included in this Facilities Needs Assessment
            2b Lighting upgrades - new interior lighting & controls                2,880 sf  $               15.00 $              43,000
            2c.1 Upgrade electrical wiring & increase electrical                  12 Safety, Security & Campus Control            $              769,000 $                 1,023,000
            outlets                               2,880 sf  $                 9.00 $              26,000  12b Safety improvements to and/or new parent/bus drop-off areas and parking
            2d Plumbing system upgrades                2,880 sf  $               11.00 $              32,000  12b.1 New Parking Lot                3,000 sf  $               16.00 $              48,000  Auto yard
            2f Energy-efficient building systems and controls (EMS                  12b.12 Repair concrete walkways           213,625 sf  $                 2.00 $            427,000
            system, per sf of Bldg)                2,880 sf  $                 7.20 $              21,000
                                                                                   12d Exterior lighting to ensure student safety                        1 ls  $       80,000.00 $              80,000
                                                                                   12e Safety locks at classroom doors                   140 ea  $             449.00 $              63,000
                                                                                   12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
          03 Site Utilities                                $                       -  $                             -  12h Fencing with controlled campus entrances
            Not included in this Facilities Needs Assessment
                                                                                    12h.2 Decorative Metal Fencing & Gates                   180 lf  $             252.00 $              45,000
                                                                                    12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $              27,000
                                                                                   12i Fire safety equipment, fire alarms and emergency lighting
          04 Classrooms New Construction                   $           2,121,000 $                 2,821,000
            4b New Construction - Classrooms                                        12i.1 Fire Alarm System                2,880 sf  $                 5.40 $              16,000
                                                                                    12i.2 Emergency Lighting                2,880 sf  $                 1.40 $                 4,000
                                                                                   12j New public address/emergency communication
            4b.8 New High School Classroom Building (1-story)                4,800 sf  $             404.00 $         1,939,000  systems                 2,880 sf  $                 7.60 $              22,000
            4b.10 Sitework & Site Improvements                4,800 sf  $               38.00 $            182,000
                                                                                   12k Intrusion alarms                   2,880 sf  $                 1.80 $                 5,000
          05 Maker Spaces & Science Labs                   $                       -  $                             -  13 District Support Facilities  $           1,516,000 $                 2,016,000
            Not included in this Facilities Needs Assessment
                                                                                   13d M&O / Warehouse / Support Facilities
                                                                                    13d.2 New M&O / Warehouse / Support                4,000 sf  $             372.00 $         1,488,000
                                                                                    13d.3 Sitework & Site Improvements                4,000 sf  $                 7.00 $              28,000
          06 Electives                                     $           5,000,000 $                 6,650,000
            6a MS/HS Electives
            6a.6 New MS/HS Electives Building              11,088 sf  $             413.00 $         4,579,000  14 Outdoor Learning Environments & Quads  $              156,000 $                    207,000
            6a.7 Sitework & Site Improvements             11,088 sf  $               38.00 $            421,000
                                                                                   14b Learning Courts
                                                                                    14b.2 New Learning Court                8,000 sf  $               19.55 $            156,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  552
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District