Page 580 - Facilities Master Plan 2016
P. 580

Lodi Unified School District                                            Lodi Unified School District
          Lodi High School                                                        Lodi High School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                             Project Cost Summary (2016$) - Lodi High School                        Project Cost Summary (2016$) - Lodi High School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            11d Learning Center                                                    15e Synthetic Track & Field
            11d.2 New Learning Center                1,100 sf  $             395.00 $            435,000  15g Field Structures
            11d.5 Sitework & Site Improvements                1,100 sf  $               38.00 $              42,000  15g1 Field House Team Rooms                1,550 sf  $             494.00 $            766,000
                                                                                    15n.1 Pool deck                       8,980 sf  $               35.00 $            314,000
                                                                                    15n.2 Pool                         12,370 sf  $             502.50 $         6,216,000
          12 Safety, Security & Campus Control             $           7,417,000 $                 9,865,000  15n.3 Bleachers                   200 seat $             708.00 $            142,000
            12a  Remaining asbestos removal             41,650 sf  $                 4.00 $            167,000  15n.4 Pool Equipment Building                2,000 sf  $             375.00 $            750,000
            12b Safety improvements to and/or new parent/bus drop-off areas and parking  15n.5 Shade Structure                2,400 sf  $               90.00 $            216,000
            12b.1 New Parking Lot            284,750 sf  $               16.00 $         4,556,000
            12b.3 Entry Plaza                     3,000 sf  $               26.00 $              78,000
            12b.6 New Access Road              60,720 sf  $               12.96 $            787,000  16 Next Generation Classroom Flexibility (Furniture)  $                       -  $                             -
            12b.11 New concrete walkways             54,500 sf  $               12.00 $            654,000  Not included in this Facilities Needs Assessment
            12d Exterior lighting to ensure student safety                        1 ls  $       80,000.00 $              80,000
            12e Safety locks at classroom doors                     15 ea  $             449.00 $                 7,000
            12f Signage for emergency response and wayfinding                        1 ls  $       40,000.00 $              40,000  17 Technology Infrastructure  $                       -  $                             -
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000  Not included in this Facilities Needs Assessment
            12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                1,121 lf  $             252.00 $            282,000
            12h.3 Rolling Decorative Metal Gate                        3 ea  $       27,000.00 $              81,000  Total Construction/Project Cost (2016$)  $      127,904,000  $170,112,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System             41,650 sf  $                 5.40 $            225,000
            12i.2 Emergency Lighting             41,650 sf  $                 1.40 $              58,000  The following items are excluded from this budget:
            12j New public address/emergency communication                         Utility hook-up fees & City connection fees.
            systems                            41,650 sf  $                 7.60 $            317,000  Offsite work and traffic signals.
            12k Intrusion alarms               41,650 sf  $                 1.80 $              75,000  Land acquisition costs.
                                                                                   Hazardous material surveys, abatement, and disposal.
                                                                                   Escalation (Costs are in 2016$ calculated to the end of the year).
          13 District Support Facilities                   $           1,516,000 $                 2,016,000
            13d M&O / Warehouse / Support Facilities
            13d.2 New M&O / Warehouse / Support                4,000 sf  $             372.00 $         1,488,000
            13d.3 Sitework & Site Improvements                4,000 sf  $                 7.00 $              28,000
          14 Outdoor Learning Environments & Quads         $           1,100,000 $                 1,463,000
            14a Main Student Quad
            14a.2 New Main Student Quad             78,750 sf  $                 9.20 $            725,000
            14b Learning Courts
            14b.2 New Learning Court             12,000 sf  $               17.25 $            207,000
            14d Student Agriculture Garden             62,200 sf  $                 2.70 $            168,000
           15 Exterior Play Spaces, Playfields & Hardcourts  $         11,329,000 $              15,068,000
            15b PE Play Yard & Hardcourts
            15b.4 Shade Structure                 3,600 sf  $               90.00 $            324,000
            15b.6 New Hardcourts               69,000 sf  $               11.00 $            759,000
            15b.8 Basketball Court/Sports Equipment                        1 ls  $       76,000.00 $              76,000
            15c Playfields
            15c.1 Repair Playfields           129,000 sf  $                 3.00 $            387,000
            15d Baseball/Softball Fields
            15d.1 Softball field - natural turf           113,354 sf  $                 9.75 $         1,105,000
            15d.3 Pitching mound/bases, per field                        1 ea  $       22,000.00 $              22,000
            15d.4 Backstops, per field                        1 ea  $       27,000.00 $              27,000
            15d.5 Dugouts, per field                        2 ea  $       81,000.00 $            162,000
            15d.6 Scoreboards                             1 ea  $       63,000.00 $              63,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  551
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District