Lodi Unified School District                                            Lodi Unified School District
          Morada Middle School                                                    Morada Middle School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                           Project Cost Summary (2016$) - Morada Middle School                     Project Cost Summary (2016$) - Morada Middle School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
            10b Staff Collaboration/Work Rooms
            10b.3 Reconfigure Staff Collaboration/Work Rooms                1,440 sf  $             235.00 $            338,000  16 Next Generation Classroom Flexibility (Furniture)  $              225,000 $                    225,000
                                                                                   16a Flexible furniture (Per Classroom, Direct Cost)                     15 ea  $       15,000.00 $            225,000
          11 Library & Student Support Services            $           3,170,000 $                 4,216,000
            11b Middle School/High School Library/Innovation Lab                  17 Technology Infrastructure                    $                 32,000 $                      32,000
            11b.2 New Library/Innovation Lab                5,852 sf  $             438.48 $         2,566,000  2-story   17c MDF and IDF data rooms with environmental control
            11b.5 Sitework & Site Improvements                2,926 sf  $               38.00 $            111,000  (direct cost only)                         1 ea  $       32,000.00 $              32,000
            11d Learning Center
            11d.4 Reconfigure Learning Center                2,080 sf  $             237.00 $            493,000
                                                                                  Total Construction/Project Cost (2016$)         $         34,204,000  $45,405,000
          12 Safety, Security & Campus Control             $           2,576,000 $                 3,426,000
            12a  Remaining asbestos removal             38,396 sf  $                 4.00 $            154,000  The following items are excluded from this budget:
            12b Safety improvements to and/or new parent/bus drop-off areas and parking  Utility hook-up fees & City connection fees.
            12b.1 New Parking Lot              91,510 sf  $               16.00 $         1,464,000  Offsite work and traffic signals.
            12b.3 Entry Plaza                     2,125 sf  $               26.00 $              55,000  Land acquisition costs.
            12d Exterior lighting to ensure student safety                        1 ls  $       20,000.00 $              20,000  Hazardous material surveys, abatement, and disposal.
            12e Safety locks at classroom doors                     40 ea  $             449.00 $              18,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            12f Signage for emergency response and wayfinding                        1 ls  $       16,000.00 $              16,000
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000
            12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                   755 lf  $             252.00 $            190,000
            12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $              27,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System             38,396 sf  $                 5.40 $            207,000
            12i.2 Emergency Lighting             38,396 sf  $                 1.40 $              54,000
            12j New public address/emergency communication
            systems                            38,396 sf  $                 7.60 $            292,000
            12k Intrusion alarms               38,396 sf  $                 1.80 $              69,000
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $              489,000 $                    650,000
            14a Main Student Quad
            14a.2 New Main Student Quad             19,950 sf  $               17.25 $            344,000
            14b Learning Courts
            14b.2 New Learning Court                7,000 sf  $               20.70 $            145,000
           15 Exterior Play Spaces, Playfields & Hardcourts  $           1,427,000 $                 1,898,000
            15b PE Play Yard & Hardcourts
            15b.4 Shade Structure                 2,400 sf  $               90.00 $            216,000
            15b.5 Resurface & Repair Hardcourts             24,000 sf  $                 5.00 $            120,000
            15b.6 New Hardcourts               24,000 sf  $               11.00 $            264,000
            15b.8 Basketball Court/Sports Equipment                        1 ls  $       12,666.67 $              13,000
            15c Playfields
            15c.1 Repair Playfields           228,600 sf  $                 3.00 $            686,000
            15h DG Track                          1,315 lf  $               97.00 $            128,000


         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  547
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District