Page 572 - Facilities Master Plan 2016
P. 572

Lodi Unified School District                                            Lodi Unified School District
          Christa McAuliffe Middle School                                         Christa McAuliffe Middle School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Christa McAuliffe Middle School         Project Cost Summary (2016$) - Christa McAuliffe Middle School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                   9d MS / HS Weight Room
          01 Modernize & Reconfigure Aging Classrooms      $                       -  $                             -  9d.4 New Weight Room                1,760 sf  $             404.00 $            711,000
            Not included in this Facilities Needs Assessment                        9d.5 Sitework & Site Improvements                1,760 sf  $               38.00 $              67,000
          02 Existing Building Systems & Toilets           $                       -  $                             -  10 Administration & Staff Support  $              310,000 $                    412,000
            Not included in this Facilities Needs Assessment                       10b Staff Collaboration/Work Rooms
                                                                                    10b.4 New Staff Collaboration/Work Rooms                   702 sf  $             423.36 $            297,000  2-story
                                                                                    10b.5 Sitework & Site Improvements                   351 sf  $               38.00 $              13,000
          03 Site Utilities                                $                       -  $                             -
            Not included in this Facilities Needs Assessment
                                                                                  11 Library & Student Support Services           $              531,000 $                    706,000
                                                                                   11d Learning Center
          04 Classrooms New Construction                   $           7,994,000 $              10,632,000  11d.4 Reconfigure Learning Center                2,240 sf  $             237.00 $            531,000
            4b New Construction - Classrooms
            4b.1 Remove Portable Classrooms                        6 ea  $       11,000.00 $              66,000
                                                                                  12 Safety, Security & Campus Control            $              389,000 $                    517,000
            4b.7 New Middle School Classroom Building (2-story)             15,322 sf  $             449.00 $         6,879,000  12b Safety improvements to and/or new parent/bus drop-off areas and parking
            4b.10 Sitework & Site Improvements                7,661 sf  $               38.00 $            291,000  12b.1 New Parking Lot                2,400 sf  $               16.00 $              38,000
            4d Student Collaboration Lab                                            12b.10 Slurry Coat & Stripe Existing Paving             59,429 sf  $                 2.00 $            119,000
            4d.1 New Student Collaboration Lab, 2- Story                1,702 sf  $             426.60 $            726,000  12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000
            4d.2 Sitework & Site Improvements                   851 sf  $               38.00 $              32,000  12e Safety locks at classroom doors                     55 ea  $             449.00 $              25,000
                                                                                   12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
                                                                                   12g Marquee Sign                               1 ea  $       10,000.00 $              10,000
          05 Maker Spaces & Science Labs                   $              338,000 $                    450,000  12h Fencing with controlled campus entrances
            5b MS / HS Science Labs                                                 12h.2 Decorative Metal Fencing & Gates                   185 lf  $             252.00 $              47,000
            5b.3 Reconfigure MS / HS Science Labs Building                 2,560 sf  $             132.00 $            338,000  12i Fire safety equipment, fire alarms and emergency lighting
                                                                                    12i.1 Fire Alarm System                4,800 sf  $                 5.40 $              26,000
                                                                                    12i.2 Emergency Lighting                4,800 sf  $                 1.40 $                 7,000
          06 Electives                                     $           4,330,000 $                 5,759,000  12j New public address/emergency communication
            6a MS/HS Electives                                                     systems                                4,800 sf  $                 7.60 $              36,000
            6a.6 New MS/HS Electives Building                 9,310 sf  $             446.04 $         4,153,000  2-story  12k Intrusion alarms                4,800 sf  $                 1.80 $                 9,000
            6a.7 Sitework & Site Improvements                4,655 sf  $               38.00 $            177,000
                                                                                  13 District Support Facilities                  $                       -  $                             -
          07 Performing Arts Improvements                  $                       -  $                             -  Not included in this Facilities Needs Assessment
            Not included in this Facilities Needs Assessment
                                                                                  14 Outdoor Learning Environments & Quads        $              428,000 $                    569,000
          08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                       -  $                             -  14a Main Student Quad
            Not included in this Facilities Needs Assessment                        14a.2 New Main Student Quad                6,200 sf  $               23.00 $            143,000
                                                                                   14b Learning Courts
                                                                                    14b.2 New Learning Court             14,600 sf  $               19.55 $            285,000
          09 Physical Education Improvements               $           6,908,000 $                 9,188,000
            9a New Gym and Lobby/Concessions
            9a.4 New Gymnasium                 10,010 sf  $             409.00 $         4,094,000  15 Exterior Play Spaces, Playfields & Hardcourts  $           1,146,000 $                 1,524,000
            9a.5 Sitework & Site Improvements             10,010 sf  $               38.00 $            380,000  15b PE Play Yard & Hardcourts
            9b Changing/Locker Rooms                                                15b.4 Shade Structure                 2,400 sf  $               90.00 $            216,000
            9b.4 New Changing/Locker Rooms                1,595 sf  $             512.00 $            817,000  15b.7 Slurry Coat & Stripe Existing Hardcourts             36,000 sf  $                 3.00 $            108,000
            9b.5 Sitework & Site Improvements                1,595 sf  $               38.00 $              61,000  15c Playfields
            9c PE/Fitness Labs                                                      15c.1 Repair Playfields           215,400 sf  $                 3.00 $            646,000
            9c.4 New PE/Fitness Labs                1,760 sf  $             404.00 $            711,000  15h DG Track                1,810 lf  $               97.00 $            176,000
            9c.5 Sitework & Site Improvements                1,760 sf  $               38.00 $              67,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  543
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District