          Opinion of Probable Cost                                    19-Apr-16  Opinion of Probable Cost                                     19-Apr-16
                          Project Cost Summary (2016$) - Millswood Middle School                  Project Cost Summary (2016$) - Millswood Middle School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
           9d MS / HS Weight Room
            9d.4 New Weight Room                  1,760 sf  $             404.00 $             711,000  17 Technology Infrastructure  $                         -  $                             -
            9d.5 Sitework & Site Improvements                1,760 sf  $               38.00 $               67,000  Not included in this Facilities Needs Assessment
          10 Administration & Staff Support               $                         -  $                             -  Total Construction/Project Cost (2016$)  $           11,915,000  $15,722,000
           Not included in this Facilities Needs Assessment
                                                                                 The following items are excluded from this budget:
          11 Library & Student Support Services           $                533,000 $                    709,000  Utility hook-up fees & City connection fees.
           11d Learning Center                                                    Offsite work and traffic signals.
            11d.4 Reconfigure Learning Center                2,248 sf  $             237.00 $             533,000  Land acquisition costs.
                                                                                  Hazardous material surveys, abatement, and disposal.
                                                                                  Escalation (Costs are in 2016$ calculated to the end of the year).
          12 Safety, Security & Campus Control            $                383,000 $                    509,000
           12b Safety improvements to and/or new parent/bus drop-off areas and parking
            12b.5 New Drop-off Area                9,800 sf  $               18.00 $             176,000
            12b.10 Slurry Coat & Stripe Existing Paving                8,500 sf  $                 2.00 $               17,000
            12b.11 New concrete walkways                1,800 sf  $               15.00 $               27,000
           12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $               40,000
           12e Safety locks at classroom doors                     55 ea  $             449.00 $               25,000
           12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $               32,000
           12g Marquee Sign                               1 ea  $       10,000.00 $               10,000
           12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                     80 lf  $             252.00 $               20,000
           12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System                2,248 sf  $                 5.40 $               12,000
            12i.2 Emergency Lighting                2,248 sf  $                 1.40 $                 3,000
           12j New public address/emergency communication
           systems                                2,248 sf  $                 7.60 $               17,000
           12k Intrusion alarms                   2,248 sf  $                 1.80 $                 4,000
          13 District Support Facilities                  $                         -  $                             -
           Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads        $                   52,000 $                      69,000
           14b Learning Courts
            14b.2 New Learning Court                2,275 sf  $               23.00 $               52,000
          15 Exterior Play Spaces, Playfields & Hardcourts  $             1,307,000 $                 1,738,000
           15b PE Play Yard & Hardcourts
            15b.4 Shade Structure                 2,400 sf  $               90.00 $             216,000
            15b.7 Slurry Coat & Stripe Existing Hardcourts             42,500 sf  $                 3.00 $             128,000
           15c Playfields
            15c.1 Repair Playfields           278,250 sf  $                 3.00 $             835,000
           15h DG Track                           1,315 lf  $               97.00 $             128,000
          16 Next Generation Classroom Flexibility (Furniture)  $                375,000 $                    375,000
           16a Flexible furniture (Per Classroom, Direct Cost)                     25 ea  $       15,000.00 $             375,000


         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  545
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   569   570   571   572   573   574   575   576   577   578   579