Page 575 - Facilities Master Plan 2016
P. 575

Lodi Unified School District                                            Lodi Unified School District
          Morada Middle School                                                    Morada Middle School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                           Project Cost Summary (2016$) - Morada Middle School                     Project Cost Summary (2016$) - Morada Middle School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                    4b.10 Sitework & Site Improvements                8,299 sf  $               38.00 $            315,000
          01 Modernize & Reconfigure Aging Classrooms      $           1,565,000 $                 2,081,000  4d Student Collaboration Lab
            1b Replacement or repair of walls                                       4d.1 New Student Collaboration Lab, 2 - Story                2,554 sf  $             426.60 $         1,089,000
            1b.1 Replace walls                    3,840 sf  $               39.50 $            152,000  4d.2 Sitework & Site Improvements                1,277 sf  $               38.00 $              49,000
            1b.2 Repair walls                     6,720 sf  $               12.60 $              85,000
            1c Replacement or repair of windows
            1c.1 Replace windows               10,560 sf  $               18.00 $            190,000  05 Maker Spaces & Science Labs  $              700,000 $                    931,000
            1d Replacement or repair of doors (other than safety locks             5b MS / HS Science Labs
            @ classroom doors)                                                      5b.3 Reconfigure MS / HS Science Labs Building                 2,880 sf  $             243.00 $            700,000
            1d.2 Repair doors & hardware             10,560 sf  $                 4.50 $              48,000
            1e Replacement or repair of floors
            1e.1 Replace floors                   3,840 sf  $               14.40 $              55,000  06 Electives             $           1,789,000 $                 2,379,000
            1e.2 Repair floors                    6,720 sf  $               10.80 $              73,000  6a MS/HS Electives
            1f Replacement or repair of ceilings                                    6a.4 ModernizeMS/HS Electives Building                 3,456 sf  $             119.00 $            411,000
            1f.1 Replace ceilings                 3,840 sf  $               27.00 $            104,000  6a.5 Reconfigure MS/HS Electives Building                 3,264 sf  $             237.00 $            774,000
            1f.2 Repair ceilings                  6,720 sf  $                 8.10 $              54,000  6a.6 New MS/HS Electives Building                 1,277 sf  $             454.30 $            580,000  2-story
            1g Patch & Paint Interior/Exterior                                      6a.7 Sitework & Site Improvements             638.40 sf  $               38.00 $              24,000
            1g.1 Patch & paint interior             10,560 sf  $                 3.10 $              33,000
            1n Repair Existing Roofing             35,031 sf  $               14.00 $            490,000
            1o Replace Existing Roofing                9,565 sf  $               20.93 $            200,000  07 Performing Arts Improvements  $           1,580,000 $                 2,101,000
            1p Repair Existing Covered Walkways / Hallways                6,200 sf  $               13.00 $              81,000  7a Music Lab
                                                                                    7a.4 New Music Lab                    3,245 sf  $             449.00 $         1,457,000
                                                                                    7a.5 Sitework & Site Improvements                3,245 sf  $               38.00 $            123,000
          02 Existing Building Systems & Toilets           $              863,000 $                 1,148,000
            2a HVAC system upgrades             10,560 sf  $               29.00 $            306,000
                                                                                  08 Multi-Purpose Room / Food Service Improvements & Student Dining  $           1,399,000 $                 1,861,000
            2b Lighting upgrades - new interior lighting & controls             10,560 sf  $               15.00 $            158,000  8a Elementary/Middle School multipurpose rooms
            2c Electrical upgrades                                                  8a.2 Modernize Multipurpose Room             10,534 sf  $               99.00 $         1,043,000
            2c.1 Upgrade electrical wiring & increase electrical                   8c Food service areas
            outlets                            10,560 sf  $                 9.00 $              95,000  8c.2 Modernize Food Service                1,776 sf  $             175.00 $            311,000
            2d Plumbing system upgrades             10,560 sf  $               11.00 $            116,000  8c.6 New Trash Enclosure                        1 ea  $       45,000.00 $              45,000
            2e Replace aging plumbing, upgrade and/or expand
            restroom facilities
            2e.1 Modernize Existing Restroom                1,350 sf  $               83.00 $            112,000
            2f Energy-efficient building systems and controls (EMS                09 Physical Education Improvements              $           6,908,000 $                 9,188,000
            system, per sf of Bldg)             10,560 sf  $                 7.20 $              76,000  9a New Gym and Lobby/Concessions
                                                                                    9a.4 New Gymnasium                 10,010 sf  $             409.00 $         4,094,000
                                                                                    9a.5 Sitework & Site Improvements             10,010 sf  $               38.00 $            380,000
                                                                                   9b Changing/Locker Rooms
          03 Site Utilities                                $              904,000 $                 1,202,000
            (For entire campus and site)                                            9b.4 New Changing/Locker Rooms                1,595 sf  $             512.00 $            817,000
            3a Updated gas service lines           641,203 sf  $                 0.12 $              77,000  9b.5 Sitework & Site Improvements                1,595 sf  $               38.00 $              61,000
            3b Updated sewer service lines           641,203 sf  $                 0.21 $            135,000  9c PE/Fitness Labs
            3c Updated water service lines           641,203 sf  $                 0.27 $            173,000  9c.4 New PE/Fitness Labs                1,760 sf  $             404.00 $            711,000
            3d Updated electrical mains and distribution           641,203 sf  $                 0.36 $            231,000  9c.5 Sitework & Site Improvements                1,760 sf  $               38.00 $              67,000
            3e Updated storm drainage system           641,203 sf  $                 0.18 $            115,000  9d MS / HS Weight Room
            3f Electrical Capacity Upgrades                        1 ls  $     172,500.00 $            173,000  9d.4 New Weight Room                1,760 sf  $             404.00 $            711,000
                                                                                    9d.5 Sitework & Site Improvements                1,760 sf  $               38.00 $              67,000
          04 Classrooms New Construction                   $           9,224,000 $              12,268,000
            4b New Construction - Classrooms                                      10 Administration & Staff Support               $           1,353,000 $                 1,799,000
            4b.1 Remove Portable Classrooms                        6 ea  $       11,000.00 $              66,000  10a Expanded, reorganized or relocated administration
                                                                                   spaces
            4b.3 Demolish Existing Buildings             11,440 sf  $               22.00 $            252,000
                                                                                    10a.3 Reconfigure Administration                4,320 sf  $             235.00 $         1,015,000
            4b.7 New Middle School Classroom Building (2-story)             16,598 sf  $             449.00 $         7,453,000
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.2       APPENDIX                                                                                                    Facilities Master Plan  546
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District