Page 571 - Facilities Master Plan 2016
P. 571

Lodi Unified School District                                            Lodi Unified School District
          Lodi Middle School                                                      Lodi Middle School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                            Project Cost Summary (2016$) - Lodi Middle School                       Project Cost Summary (2016$) - Lodi Middle School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          11 Library & Student Support Services            $           2,695,000 $                 3,584,000  16 Next Generation Classroom Flexibility (Furniture)  $              270,000 $                    270,000
            11b Middle School/High School Library/Innovation Lab                   16a Flexible furniture (Per Classroom, Direct Cost)                     18 ea  $       15,000.00 $            270,000
            11b.2 New Library/Innovation Lab                4,840 sf  $             406.00 $         1,965,000
            11b.5 Sitework & Site Improvements                4,840 sf  $               38.00 $            184,000
            11d Learning Center                                                   17 Technology Infrastructure                    $                 32,000 $                      32,000
            11d.4 Reconfigure Learning Center                2,304 sf  $             237.00 $            546,000   17c MDF and IDF data rooms with environmental control
                                                                                   (direct cost only)                             1 ea  $       32,000.00 $              32,000
          12 Safety, Security & Campus Control             $           2,101,000 $                 2,794,000
            12a  Remaining asbestos removal             50,672 sf  $                 4.00 $            203,000  Total Construction/Project Cost (2016$)  $         38,372,000  $50,936,000
            12b Safety improvements to and/or new parent/bus drop-off areas and parking
            12b.1 New Parking Lot              22,400 sf  $               16.00 $            358,000
            12b.3 Entry Plaza                     2,700 sf  $               26.00 $              70,000  The following items are excluded from this budget:
            12b.9 Repair existing Parking Lot             53,200 sf  $                 6.30 $            335,000  Utility hook-up fees & City connection fees.
            12b.10 Slurry Coat & Stripe Existing Paving             13,240 sf  $                 2.00 $              26,000  Offsite work and traffic signals.
            12b.11 New concrete walkways                5,400 sf  $               15.00 $              81,000  Land acquisition costs.
            12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000  Hazardous material surveys, abatement, and disposal.
            12e Safety locks at classroom doors                     50 ea  $             449.00 $              22,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000
            12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                   300 lf  $             252.00 $              76,000
            12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $              27,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System             50,672 sf  $                 5.40 $            274,000
            12i.2 Emergency Lighting             50,672 sf  $                 1.40 $              71,000
            12j New public address/emergency communication
            systems                            50,672 sf  $                 7.60 $            385,000
            12k Intrusion alarms               50,672 sf  $                 1.80 $              91,000
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $              452,000 $                    601,000
            14a Main Student Quad
            14a.2 New Main Student Quad             10,400 sf  $               19.55 $            203,000
            14b Learning Courts
            14b.2 New Learning Court             12,050 sf  $               20.70 $            249,000
           15 Exterior Play Spaces, Playfields & Hardcourts  $           1,950,000 $                 2,594,000
            15b PE Play Yard & Hardcourts
            15b.4 Shade Structure                 2,400 sf  $               90.00 $            216,000
            15b.5 Resurface & Repair Hardcourts             26,400 sf  $                 5.00 $            132,000
            15b.6 New Hardcourts               24,200 sf  $               11.00 $            266,000
            15b.8 Basketball Court/Sports Equipment                        1 ls  $       38,000.00 $              38,000
            15c Playfields
            15c.1 Repair Playfields           390,000 sf  $                 3.00 $         1,170,000
            15h DG Track                          1,315 lf  $               97.00 $            128,000


         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.2       APPENDIX                                                                                                    Facilities Master Plan  542
                   DETAILED COST ESTIMATE                                                                                  Lodi Unified School District
   566   567   568   569   570   571   572   573   574   575   576