FULL SIDE WASHER
Installation
Neo-Tex Cleaning Material
Upper Hub
1) Mount the two 6” diameter x 42-1/2” tall hubs so that they set on top of the lower
hubs by securing the “Spider” Clamps to the shafts and securing the “Skins” to the
Spiders as shown. Be sure that the open ends of the “C” channels are facing
upward (FIGURE 1).
2) Locate the 41” x 8” Neo-Tex pieces that are 1/4” thick (thicker Neo-Tex material).
Fold them in half and place one in the first, middle and last slot of each skin of the
hub, making sure they are pushed all the way to the bottom (FIGURE 2).
3) Locate the 25” x 8” Neo-Tex pieces that are 1/8” thick (thinner Neo-Tex material).
Load two pieces onto each 8” clip to provide the fill for this row. Place 12 of these
assemblies into the previous slots filled to continue stacking the upper hub.
4) Locate the 25” x 8” Neo-Tex pieces that are 1/4” thick (thicker Neo-Tex material).
Load one piece onto each 8” clip to provide the fill for this row. Place 12 of these
assemblies into the previous slots filled to continue stacking the upper hub.
5) Locate the 28” x 8” Neo-Tex pieces that are 1/4" thick (thicker Neo-Tex material).
Load one piece onto each 8” clip to provide the fill for this row. Place 12 of these
assemblies into the previous slots filled to continue stacking the upper hub.
6) Locate the 32” x 10” Neo-Tex pieces that are 1/4" thick (thicker Neo-Tex material)
Load one piece onto each 10” clip to provide the fill for this row. Place 12 of these
assemblies into the previous slots filled to continue stacking the upper hub.
First, middle
and last slot
FIGURE 2 of a skin
Upper Hub
(Top view)
FIGURE 1 Top Row 32” x 10”
Insert into one 10” clip.
FIGURE 3