QUICKFIRE® WRAP AROUND


             Installation


             Securing the Head Assembly to the Boom: Hydraulic

                 Locate the two side-wheel shafts.
                    1)  Loosen both setscrews in each of the shaft bearings.
                                              Close-up view of head assembly.







                       Bearing set screw
                              (typical)








                    4)  Locate the accessory box and separate its contents.
                    5)  Slide the shaft up through both bearings until the shaft of the hydraulic motor is inside of the side-
                       wheel shaft.
                    Note:  Woodruff Key is to be inserted in the Hydraulic Motor Shaft.

                    6)  Slide the supplied Woodruff Key into the slot at the top of the shaft.
                    7)  Secure  the supplied split-locking collar into position as shown below. This will hold the shaft in
                       place. Be sure that the Woodruff Key is positioned at 90° to the split in the collar as shown
                       in the image below.


                                                                Hydraulic Motor shaft
                      Split locking collar                      Woodruff key

                         Shaft bearing                          Split locking collar




                                                                                        Top View






                    8)  Tighten all the setscrews on both bearings.