2018 National Home Improvement Estimator, All Rights Reserved                                    Page 15



            Labor Costs and Crews
            Throughout this manual you'll see a column headed Craft@Hrs. Letters and numbers in this column
            show our estimates of:

            • Who will do the work (the craft code)
            • An @ symbol which means "at"
            • How long the work will take (manhours)

            For example, in Chapter 4, Page 70, you'll find estimates for installing BC plywood wall sheathing by the
            square foot. The Craft@Hrs column opposite 1/2" plywood wall sheathing shows:

            B1@.016

            That means we estimate the installation rate for crew B1 at 0.016 manhours per square foot. That's the
            same as 16 manhours per 1,000 square feet.


            Figure 1-4 is a table that defines each of the craft codes used in this book. Notice that crew B1 is
            composed of two craftsmen: one laborer and one carpenter. To install 1,000 square feet of 1/2" BC wall
            sheathing at 0.016 manhours per square foot, that crew would need 16 manhours (one 8-hour day for a
            crew of two).

            Notice also in the table that the cost per manhour for crew B1 is listed as $33.44. That's the average for
            a laborer (listed at $29.93 per hour) and a carpenter (listed at $36.94 per hour): $29.93 plus $36.94 is
            $66.87. Divide by 2 to get $33.44, the average cost per manhour for crew B1.

            In the table below, the cost per manhour is the sum of hourly costs of all crew members divided by the
            number of crew members. That's the average cost per manhour.

            Costs in the Labor column in this book are the product of the installation time (in manhours) multiplied
            by the cost per manhour. For example, in Chapter 4, the labor cost listed for 1/2" BC wall sheathing is
            $0.54 per square foot. That's the installation time (0.016 manhours per square foot) multiplied by $33.44,
            the average cost per manhour for crew B1.

                                                                Craft  Cost Per  Crew
                                                                Code  Manhour  Composition
                                                                B1  $33.44  1  laborer and 1  carpenter
                                                                B2  $34.60  1  laborer and 2  carpenters
                                                                B3  $32.27  2  laborers and 1  carpenter
                                                                B4  $36.90  1  laborer
                                                                               1  operating engineer
                                                                               1  reinforcing iron worker
                                                                B5  $36.57  1  laborer, 1  carpenter
                                                                               1  cement mason
                                                                               1  operating engineer
                                                                               1  reinforcing iron worker
                                                                B6  $32.48  1  laborer, 1  cement mason
                                                                B7  $30.32  1  laborer, 1  truck driver
                                                                B8  $36.03  1  laborer, 1  operating engineer
                                                                B9  $32.62  1  bricklayer, 1  bricklayer's helper
                                                                BB  $37.47  1  bricklayer
                                                                BC  $36.94  1  carpenter
                                                                BE  $40.04  1  electrician
                                                                BF  $33.79  1  floor layer
                                                                BG  $35.68  1  glazier