2018 National Home Improvement Estimator, All Rights Reserved Page 39
Day Week Month
Equipment Rental for Foundations and Slabs.
Buggies, push type, 7 CF 78.00 464.00 803.00
Buggies, walking type, 12 CF 110.00 263.00 762.00
Buggies, riding type, 14 CF 143.00 425.00 761.00
Buggies, riding type, 18 CF 115.00 361.00 747.00
Vibrator, electric, 3 HP, flexible shaft 64.00 200.00 480.00
Vibrator, gasoline, 6 HP, flexible shaft 83.00 246.00 735.00
Troweling machine, 36", 4 paddle 68.00 215.00 590.00
Cement mixer, 6 CF 100.00 279.00 625.00
Towable mixer (10+ CF) 104.00 312.00 626.00
Power trowel 36", gas, with standard handle 68.00 215.00 590.00
Bull float 14.00 43.00 103.00
Concrete saws, gas powered, excluding blade cost
10 HP, push type 110.00 295.00 685.00
20 HP, self propelled 160.00 470.00 1,200.00
37 HP, self propelled 260.00 785.00 1,760.00
Concrete conveyor, belt type, portable, gas powered,
all sizes 139.00 510.00 1,460.00
Vibrating screed, 16', single beam 86.00 265.00 588.00
Column clamps, to 48", per set -- -- 8.00
Skid steer loaders
Bobcat 643, 1,000-lb. capacity 230.00 770.00 1,780.00
Bobcat 753, 1,350-lb. capacity 220.00 710.00 1,590.00
Bobcat 763, 1,750-lb. capacity 260.00 770.00 1,790.00
Bobcat 863, 1,900-lb. capacity 265.00 800.00 2,900.00
Skid steer attachments
Auger 130.00 410.00 840.00
Hydraulic breaker 180.00 530.00 1,520.00
Backhoe 115.00 270.00 1,090.00
Sweeper 145.00 355.00 860.00
Grapple bucket 55.00 160.00 470.00
Trenchers, inclined chain boom type, pneumatic tired
15 HP, 12" wide, 48" max. depth, walking 199.00 577.00 1,570.00
20 HP, 12" wide, 60" max. depth, riding 300.00 880.00 1,820.00
Wheel loaders, front-end load and dump, diesel
3/4 CY bucket, 4WD, articulated 180.00 615.00 1,840.00
1 CY bucket, 4WD, articulated 315.00 915.00 2,250.00
2 CY bucket, 4WD, articulated 470.00 1,380.00 3,760.00
Vibro plate, 300 lb, 24" plate width, gas 125.00 400.00 920.00
Vibro plate, 600 lb, 32" plate width, gas 260.00 700.00 1,640.00
Rammer, 60 CPM, 200 lb, gas powered 93.00 270.00 610.00
Craft@Hrs Unit Material Labor Total
Concrete pumping. Using a trailer-mounted gasoline pump.
3/8" aggregate mix (pea gravel), using hose to 200'
Cost per cubic yard (pumping only) --@.000 CY -- -- 16.65
Add for hose over 200', per LF --@.000 LF -- -- 2.08
3/4" aggregate mix, using hose to 200'
Cost per cubic yard (pumping only) --@.000 CY -- -- 17.17
Add for hose over 200', per LF --@.000 LF -- -- 2.08