Page 79 - 2018 National Home Improvement
P. 79

2018 National Home Improvement Estimator, All Rights Reserved                                    Page 62



            Framing Repairs

            Pricing for floor framing repairs. Place temporary 6" x 6" x 10' needle beam under joists for floor
            jacking, using 4" x 4" pre-cut cribbing for end supports. Includes removing the needle beam when lifting
            is complete. All jacking materials to be salvaged. No concrete work included.
              Beam set in a basement or first floor         B1@1.72   Ea         --    62.69      62.69
              Beam set in a crawl space                     B1@3.44   Ea         --   125.40     125.40
            Remove a floor beam. Includes jacking and cutting out the old beam. Add the cost of repairs to
            sheathing, siding and interior finish. Assumes all jacking materials are salvaged. Add the cost of the
            beam from the section that follows. Add needle beam placement costs from the lines above. Lifting and
            lowering should be done slowly. A good rule is to lift no more than 1/4" per day.
              Per   8' section, basement or first floor     B1@6.87   Ea         --   250.40     250.40
              Per 16' section, basement or first floor      B1@9.34   Ea         --   340.40     340.40
              Per   8' section, work in a crawl space       B1@10.3   Ea         --   375.40     375.40
              Per 16' section, work in a crawl space        B1@14.0   Ea         --   510.30     510.30
            Needle beam, purchase
              6" x 6" x 10', green No. 1 Douglas fir         --@.000  Ea     44.64         --     44.64
            Cribbing, 4" x 4" x 8' No. 2 fir
              Per crib, purchase                             --@.000  Ea     10.10         --     10.10
            Bottle (hydraulic) jack. Two-piece handle with internal overload valve, 9" to 18" lift
                6 ton capacity, purchase                     --@.000  Ea     29.69         --     29.69
              12 ton capacity, purchase                      --@.000  Ea     40.70         --     40.70
              20 ton capacity, purchase                      --@.000  Ea     57.47         --     57.47

            Beams and girders. Std & Btr. First floor work. See beam removal costs in the previous section. Crawl
            space work assumes a minimum 24" high reasonably accessible area. Work done in crawl spaces less
            than 24" high may cost up to 100% more. Figures in parentheses show board feet per linear foot of
            beam or girder, including 7% waste.
              4" x   6", per MBF                            B1@16.0 MBF     983.74    583.20    1,566.94
              4" x   8", 10", 12", per MBF                  B1@16.0 MBF     983.74    583.20    1,566.94
              6" x   6", per MBF                            B1@16.0 MBF 1,616.00      583.20    2,199.20
              6" x   8", 10", 12", 8" x 8", per MBF         B1@16.0 MBF 1,616.00      583.20    2,199.20
              4" x   6" (2.15 BF per LF)                    B1@.034   LF      2.11       1.24       3.35
              4" x   8" (2.85 BF per LF)                    B1@.045   LF      2.81       1.64       4.45
              4" x 10" (3.58 BF per LF)                     B1@.057   LF      3.52       2.08       5.60
              4" x 12" (4.28 BF per LF)                     B1@.067   LF      4.21       2.44       6.65
              6" x   6" (3.21 BF per LF)                    B1@.051   LF      5.20       1.86       7.06
              6" x   8" (4.28 BF per LF)                    B1@.067   LF      6.93       2.44       9.37
              6" x 10" (5.35 BF per LF)                     B1@.083   LF      8.67       3.03     11.69
              6" x 12" (6.42 BF per LF)                     B1@.098   LF     10.40       3.57     13.98
              8" x   8" (5.71 BF per LF)                    B1@.088   LF      9.24       3.21     12.45
              Add if replacing a beam, basement or first floor  B1@.047  LF      --      1.71       1.71
              Add if replacing a beam in a crawl space      B1@.095   LF         --      3.46       3.46

            Shim up a floor beam. Jack a floor beam into position with a crossarm mounted on a hydraulic jack.
            Insert a pressure-treated shim above the pier or column and remove the jack. Per jacking point. Work
            done on sloping or unstable ground will cost more. Assumes all jacking materials are salvaged and
            includes cost of removing the jack. Lifting and lowering should not exceed 1/4" per day.
              Jacking done in a basement                    B1@.700   Ea      2.53     25.52      28.05
              Jacking done in a crawl space                 B1@1.25   Ea      2.53     45.56      48.09
   74   75   76   77   78   79   80   81   82   83   84