Addendum No. 2 dated April 11, 2017
Attachment 6
Estimated Project Schedule (Due Dates)
• Design-Builder Selected – May 2, 2017
• Contract Finalized – May 24, 2017
• Notice to Proceed with Design – May 24, 2017
• Design 50 percent – June 24, 2017
• Design 100 percent w/Tax Collector review – July 13, 2017
• Submit for Permit – July 13, 2017
• Notice to Proceed with Construction – Aug 12, 2017
• Majority of Sitework Completed – Nov. 30, 2017
• Substantial Completion – April 9, 2018
• Final Completion – April 26, 2018