INTEGRATED PROJECT DELIVERY
• The MacLeamy Curve is a graph of the decisions mapped along the timeline of a
typical construction projects. It clearly shows that decisions made early in a project
(during design) can be made at lower cost and with greater effectiveness.
MacLeamy Curve describes:
1 – Early involvement of FMC at preliminary design stage have more ability to impact
cost and performance of the project
2 – Cost of design changes will be lower at preliminary design stage of the project
3 – Traditional practice for project construction documentation
4 – Integrated – Smart building practice of project delivery by having more diverse
expertise (i.e., more interested parties) in the room during design
11