Page 15 - QDigitz
P. 15
Q!Digitz Vol 1 Aug 2019
Check for the updated list of migration ready Post Migration Report & Acceptance
components/server/data/application
The success criteria meeting, performance
Pilot Report (As Applicable) measures, recorded issues/resolution, etc. Check
for the approval.
Check for Go/No Go Decision and the
challenges/risks & lessons learnt documented. The Pre & Post Migration Technical Review Checklist
lessons to be taken to migration activities.
Check if the project team used the pre & post
Migration schedule migration checklist & any tool for evaluating the
migration. Also, the checklists are used in the
Check for the intermediate milestones and project.
percentage completion planned. Check for
dependencies identi ed for meeting schedules Migration Metrics
and the risks.
Agree with project on the migration metrics and
Master list with con guration details and Status review the data on a monthly basis/ biweekly
(&/) Run Book basis. De ned threshold and violations supported
with analysis
Check for the schedule, Status of Migration,
Pending issues, Runbook - Detailed steps/activities The checks on the above given activities and
with con gurations & checkpoints & status detail deliverables will enable the cloud migration to
resolve the challenges quickly and to have a clear
Test Report view on work items progress. Often migration is
the process weakly addressed after an
enthusiastic start. Then based on time availability,
Check for the functional, security, and the depth of migration happens in the accounts,
performance test cases and the test report which often impacts the quality of migration. So
it's important for us to ensure a right level of
Cut Over Plan progress happens in every front in migration. The
above given thought process can help in building
Check for the Readiness and Roll back plan. stronger connect.
Training Plan & Records
Training materials, training plan and training
report/Completion details to be maintained for
user/client