SECTION U



                                         PAINTING AND DECORATING

                     Generally


               U.1  Information

                     1.   Work shall be classified as follows and given under an appropriate heading:

                          a.    New work internally.
                          b.    New work externally.
                          c.    Repainting and redecoration work internally.
                          d.    Repainting and redecorating work externally.

                     2.   Redecoration or work of a restorative nature shall be particularly described.

                     3.   Work required to be carried oUt in members before they are fixed shall be so described,
                          stating if specifically required to be carried out on or off site

                     4    Work to ceilings and beams over 3.50m above floor (measured to ceiiing level in both
                          cases) shall be so described stating the height in further stages of 1.50m.

               U.2  Measurement

                      Work shall be measured the area covered and allowances made (unless otherwise provided
                     herein) for the extra girth of edges, mouldings, panels, sinkings, corrugations, flutings, carvings,
                     enrichments and the like. No deduction shall be made for voids not exceeding o SOm2

                     Painting, polishing and similar work

               U.3  Generally

                     1.   Particulars of the following shall be given:

                          a.   Kind and quality of matefials.
                          b.   NatUre of the base.
                          c.   Preparatory wofik. (e.g. rubbing  down, burning off, stripping old paper or other
                               decorations specifying the number of layers or type if appropriate, cutting out and
                               repairing cracks, knotting, stopping, staining, bodying in, etc )
                          d.   Number of priming or sealing coats.
                          e.   Number of undercoats.
                          f.   Number of finishing coats stating the sufiace finish.
                          g.   Method of application (if none stated it shall be at the Contractor's discretion).
                          h.   Rubbing down between coats with glass, emery or sand paper shall be deemed to
                               be included with the items. Particulars of any abrasive or other treatment required
                               shall be stated.

                     2.   Work on surfaces over 300mm girth shall be given in square metres. Work on isolated
                          surfaces not exceeding 300mm girth shall be given in metres stating the girth in stages of
                          150mm. Work on isolated sufiaces not exceeding 0.50m2 shall be enumerated
                          irrespective of size.