U.6   Structural metalwork

                     1.   Classification of work shall be as follows:

                          a.    Members of roof trusses.
                          b.    Surfaces of other metalwork (grouped together). Work on hookbolts, clips and the
                               like shall be deemed to be included with the purlins, rails and the like with which
                               they are associated.

               U.7   Radiators

                     Work on radiatons (measured the area to be painted) shall be so described. Work on brackets
                     and stays shall be deemed to be included.

               U.8   Railings, fences and gates

                     1.   Classitcation of work shall be as follows:

                          a.    Fencing and gates (grouped together) each side to be measured net overall
                               describing the type of fence and gate.
                          b.    Posts, rails, balusters and the like.
                          c.    Ornamental railings, gates and the like (grouped together) each side to be
                               measured overall regardless of voids.

               U.9   Gutters

                     1.    Classification of work shall be as follows:

                          a.    Valley and parapet gutters (grouped together)
                          b.    Eaves gutters.

                     2.    Work on brackets shall be deemed to be included.

               U.10  Pipes, ducts, etc.

                     1.   Classification of work shall be as follows:

                          a.   Pipes and conduits.
                          b.   Lagged pipes.
                          c.   Cables.
                          d.   Ducting and tnunking.
                          e.   Straps, standards, bars and the like.

                     2.   Work on saddles, pipohooks, holderbats, conduit boxes, other components for fixing and
                          the like shall be deemed to be included with the work on pipes and conduits.

                     3.   Work on ventilating gratings, soot-doors, f ushing cistems, rainwater-heads, strap-hinges
                          and the like shall be enumerated separately irrespective of size. Work on ventilating
                          gratings not exceeding 0.50m2 shall be given in square metres.

                     4.   Service pipes and equipment painted throughout  in coded colours shall be so described
                          stating the number of colours. Coloured bands in coding service pipes shall be
                          enumerated and described stating the number of colours.