                                                    Concept Budget Estimate 10-19-17
                                                                                         Unit
           Code                        Description                     Quantity  Unit    Cost      Amount      Total Cost
          Div 16  Electrical & Systems                                                                                      62,500
                   Electrical & Systems - Lsum                                            1  ls                      -                   -
                   Electrical                                                             1  ls          50,000.00              50,000
                   Fire Alarm System                                               5,472  gsf   Incld w above
                   Voice / Data System (Raceways & Boxes Only, No Wiring)               2,150  acsf   Incld w above
                   Lightning Protection System                                            1  ls   Incld w above
                   Light Fixture & Lighting Controls Allowance                            1  ls          12,500.00              12,500

                                                            SUBTOTAL                                                      444,014
                  General Conditions                                                                                        40,000
                  Builders Risk Insurance                                                                      By Owner
                  General Liability Insurance                                                                                 4,878
                  Building Permits Cost                                                                        By Owner
                  Impact Fees and Primary Utility Costs                                                        By Owner
                                           CONSTRUCTION BUDGET COSTS                                                      488,892
                  Budget Contingency (5%)                                                                                   22,201
                  CMAR Fee (5%)                                                                                             24,445
                  Payment and Performance Bond                                                                                6,515
                                       TOTAL CONSTRUCTION BUDGET COST                                                   542,053

                                                                      Building Relocation                      $262,000
                                                                      Building Renovations (Budget)            $280,000