Hamilton College
                                       Blood Fitness and Dance Center & Little Squash Center



































          SIZE                     OWNER
          51,175 square feet       Hamilton College

          CONTRACT TYPE            ARCHITECT
          Construction Manager-at-Risk  Butler Rogers Baskett (BRB)
                                   Architects






                                                                      PROJECT DETAILS
         Th  e state-of-the-art facility triples the previous space for fi tness and       •   Adaptive reuse and major alterations of the
         includes a glass enclosed aerobic/cardio training area that overlooks   former Saunders Hall of Chemistry created the
         Steuben Field, two rooms for resistance and weight-training, a three-  fi tness center as a new focal point of student life.
         story climbing wall, a dance studio and a multipurpose room. Built
         along the north wall of the fi eld house, the Little Squash Center features        •   Th  e Center benefi ts students on a campus
         10 regulation-size squash courts, including two with exhibition gallery   where approximately 75 percent of the student
         seating for 138 spectators.                                       body work out regularly.
                                                                          •   Aggressive scheduling included pre-purchasing
                                                                           the climbing wall, HVAC equipment, and
                                                                           fi tness equipment.
                                                                          •   Extensive study of the existing structural
                                                                           and space programming of the building, as
                                                                           well as the execution of coordinated design
                                                                           studies to decide what parts of the structure to
                                                                           salvage, what to remove, and how to introduce
                                                                           necessary upgrades to the building envelope and
                                                                           mechanical systems.