DIAGRAMA DE PERT Y RUTA CRÍTICA
Uika Itakatl
CPM
Project This file was created POM-QM for
Management Windo ws, V5
Data
Time
A 2
B 2
C 2 A B
D 2 C
E 2 D
F 2 B
G 2 A B
H 1 A B
I 1 C E
J 1 C E I
K 2
L 2 B E I J K
Results
Task Early Start Early Finish Late Start Late Finish Slack
A 0 2 0 2 0
B 0 2 0 2 0
C 2 4 2 4 0
D 4 6 4 6 0
E 6 8 6 8 0
F 2 4 10 12 8
G 2 4 10 12 8
H 2 3 11 12 9
I 8 9 8 9 0
J 9 10 9 10 0
K 0 2 8 10 8
L 10 12 10 12 0
Project 12