Page 7 - FQ10591.PloteConstruction.IL.For-ReadyMixBatchPlant.DC15000S w5000GalTank wDuplexDelPumpPkg
P. 7

Page No. 5
                                                                                Proposal No. Q10591
                                                                                Date:   October 12, 2017


                            C.      Disconnect switches and reattachment of wiring and prepiped
                                    subassemblies.

                            D.      Electrical/Mechanical utility service to the heater.

                                    D.1    Power *460 Volts, 3 Phase, 60 Hertz to blower and pump.

                                    D.2    Control 115 Volts, 1 Phase, 60 Hertz to heater and burner control
                                           panel.

                            E.      System is knocked down for shipment and requires re-assembly.

                            F.      Piping from the heater overflow to a drain.

                            G.      Installation and hook-up of equipment prior to visit from Ludell Field
                                    Engineer.

                            H.      Local permits and approvals, if applicable.

                            I.      Insulation and jacketing of tank, if desired.


               Note IV - Optional Offer   (Available Upon Request)

                            A.      Ludell offers dual gas trains for use with either propane or natural gas.  In
                                    addition, various types of gas trains are available, which meet GE GAP
                                    (formerly IRI), AGA, and CGA specifications.

                            B.      Spare parts kit.

                            C.      Extra stack sections, elbows and rain caps.

                            D.      Shorter configurations, when reduced height is required for lower ceiling
                                    height.