Page 7 - FQ10482.IveyMechanical.TN.15000S w5000 Gal Tank
P. 7

Page No. 6
                                                                                Proposal No. Q10482
                                                                                Date:  April 12, 2017

               Note III - Customer to Provide

                            A.      Constant minimum gas pressure to the entrance of the gas train of:  5 PSIG
                                    @ 15,000 FT /HR.
                                               3

                            B.      Constant water pressure to the entrance of the water heater of:  30 PSIG
                                    minimum at 300 GPM

                                    B.1    Ludell can furnish a booster pump with necessary controls at added
                                           cost, if required to obtain 30 PSIG minimum constant water
                                           pressure.

                            C.      Disconnect switches and reattachment of wiring and prepiped
                                    subassemblies.

                            D.      Electrical/Mechanical utility service to the heater.

                                    D.1    Power *460 Volts, 3 Phase, 60 Hertz to blower and pump.

                                    D.2    Control 115 Volts, 1 Phase, 60 Hertz to heater and burner control
                                           panel.

                            E.      Piping from the heater overflow to a drain.

                            F.      Installation and hook-up of equipment prior to visit from Ludell Field
                                    Engineer.

                            G.      Local permits and approvals, if applicable.


               Note IV - Optional Offer   (Available Upon Request)

                            A.      Ludell offers dual gas trains for use with either propane or natural gas.  In
                                    addition, various types of gas trains are available, which meet GE GAP
                                    (formerly IRI), AGA, and CGA specifications.

                            B.      Spare parts kit.

                            C.      Variable frequency drives and pressure transducers for hot water pumps.

                            D.      Larger capacity hot water storage tanks are available.

                            E.      Low NOX emission (30 ppm) with use of Flue Gas Recirculation (FGR).