Coal Mill Explosion











           1    What is the name of the       2    What are its specific objectives related to the Priority Unwanted
                critical control for Coal Mill
                                                   Event (PUE)?
                Explosion?
          Inertization                       Early detection of change in process parameters such as Temperature and CO level, and
                                             automatically initiate the inertization sequence to prevent the formation of an explosive
                                             atmosphere by having an inert atmosphere (either N2 or CO2) that could effectively
                                             achieve a minimum of 2% below Limiting Oxygen Concentration. Provision of a manual
                                             intertization from the Central Control Room (CCR) if a fire or smouldering detected by a
                                             passerby

           3    What are the critical         4    What are the activities       5    What can be sampled from
                control performance
                                                   within the management
                                                                                      the set of activities for
                requirements to meet the           systems that support               verification, providing a
                objectives?                        having the critical control        clear image of the critical
                                                   able to do what is required?       control status?
          Pre-defined Solenoid valve opening   Safety philosophy and alarm setpoints   Operators can manually initiate
          position with a high-high level trip on   are included in Standard Operating   inertization by remote push button or
          Temperature and CO                 Procedure (SOP)                    via CCR

          Control system elements - Temperature   Scheduled preventative maintenance   Percentage of PM completion rate
          transmitter, CO analyser, Solenoid valves   and calibration in CMMS as per   Number of defects found during
          are periodically calibrated, along with a   manufacturer’s requirements/ Corporate   calibration and PMs. (This should be
          suitable preventative maintenance (PM)   CEM guidance                 documented in CMMS)
          schedule and free of build-up or any   Classified as highest priority and
          obstruction                        critical equipment in Computerized
                                             Maintenance Management System
                                             (CMMS)

          Periodic ‘end to end’ Trip testing    Scheduled end to end trip testing in CMMS  Completion rate of trip testing
          (min once a year)                  Report deviation/failure as near-miss on   Number of failed Trips upon testing
                                             iCare

          Instruments and equipment associated   A systematic approach across the plant   Number of non compliance to the
          with inertization system are coloured or   to identify, colour or tag as “critical” - This   defined systematic approach
          tagged as “Critical Control” in the field  should be visual as well as identifiable in
                                             CMMS


          All manual isolation valves are locked   Regular visual inspection of the area and   Number of non compliance to the
          open or the valve handles are removed   installation                  defined systematic approach
          at an open position

          Inert medium (N2 or CO2) maintained full   Regular (daily) tank inventory checks  Percentage of PM completion rate
          level in the tank/s                Scheduled PMs for tank, pipes, valves,    Number of deferred PMs
                                             and gauges                         Number of defects found during
                                                                                calibration and PMs. (This should be
                                                                                documented on CMMS)

           6    What is the target performance for critical     7    What is the critical control performance
                                                                     trigger for shutdown, critical control review or
                control?
                                                                     investigation?

          All the inspection, maintenance and testings are carried out   Failed inertization upon testing
          100% without any deferments. The inertization sequence is fully   Unauthorised deferment without Plant Manager’s written
          effective during tests                               authorisation



          Creation date: 01/2021 • The latest and only controlled version of this document is available on the HSE intranet.
          © 2021 Holcim - For internal use only