Page 35 - Critical Control flipbook_Neat
P. 35

Contact with Hot Meal











           1    What is the name of the       2    What are its specific objectives related to the Priority Unwanted
                critical control for Contact
                                                   Event (PUE)?
                with Hot Meal?
          Early Detection of build ups       Provisions for 1) priority warning on high alarms to trigger process adjustments by CCR
          and blockages                      operator (up to stopping the kiln) and  2) automatic kiln emergency stop on high-high
                                             alarms


           3    What are the critical         4    What are the activities       5    What can be sampled from
                control performance
                                                   within the management
                                                                                      the set of activities for
                requirements to meet the           systems that support               verification, providing a
                objectives?                        having the critical control        clear image of the critical
                                                   able to do what is required?       control status?
          Kiln feed trips on high-high level of   Annual testing of interlocked kiln   Completion rate of annual trip testing
          cyclone blockage detection (or fan   emergency stoppage is scheduled   Number of times a high-high alarm
          trip) and automatically triggers kiln   in Computerized Maintenance   failed to automatically trip (review of
          emergency stoppage (automatic      Management System (CMMS)           signal history)
          deferred response)                 Failures to trip documented and reported
                                             as critical incident in iCare

           Central Control Room (CCR) Operator   Alarm setpoints are included in Standard   Operators confirm they have ability and
          receives high priority warning alarm of   Operating Procedure (SOP)   authority to stop kiln during emergency
          cyclone blockage detection and build-up   Operators understand the SOP and are
          levels (e.g. pressure drop and temps)  empowered to start emergency kiln
                                             stoppage

          Critical instrumentation provides reliable   Scheduled preventative maintenance and   Percentage of PM completion rate
          signals                            calibration in CMMS as per manufacturer’s   Number of deferred PMs
                                             requirements/Corporate CEM guidance  Number of defects found during
                                             Classified as highest priority and critical   calibration and PMs
                                             equipment in CMMS

          CCR Operator receives timely information   Patroller routine inspection includes   Operators confirm they have ability and
          of Kiln back-end condition and amount   condition of kiln back-end area and   authority to stop kiln during emergency
          of hot meal leakage                assessment of hot meal leakage
                                             Action triggers for kiln stoppage are
                                             included in SOP for CCR Operator


           6    What is the target performance for critical     7    What is the critical control performance
                                                                     trigger for shutdown, critical control review or
                control?
                                                                     investigation?
          All the inspection, maintenance and testings are carried out   Kiln emergency stoppage not started upon automatic demand
          100% without any deferments. The kiln emergency stoppage   from the critical sensors. Kiln emergency stoppage not started
          sequence is fully effective during tests             by operator: failure to follow the SOP for emergency kiln
                                                               stoppage. Unauthorised maintenance deferment without Plant
                                                               Manager’s written authorisation













          Creation date: 01/2021 • The latest and only controlled version of this document is available on the HSE intranet.