NAVFAC SOUTHWEST P-918 SPECIAL
                                                                                                                                  OPERATIONS FORCES CLOSE COMBAT FACILITY
                                                                                                                                        NAVAL BASE CORONADO, CALIFORNIA
               DELIVERY GROUPS


              A SELECTION OF 2021 FEDERAL CLIENTS













                                                      “ The staff (Haskell)
                                                       provided exceptional
                                                       management control

                                                       over the contract. This
                                                       team of professionals              LEGACY PROJECTS
                                                       provided a higher                  We were unable to achieve the 2021 sales budget due to a planned
                                                       level of internal                  hiatus in project pursuits and our increased selectivity in approving
                                                                                          pursuits. In October, we were awarded a $22 million U.S. Coast Guard
                                                       communication that
                             NAVFAC MID-ATLANTIC P-464                                    project in Atlantic Beach, North Carolina. The Federal Division generated
                          AIRCRAFT MAINTENANCE HANGAR   benefited the project.”           $76.8 million in revenue and a net loss of $10.7 million primarily due
                               MARINE CORPS AIR STATION
                             BEAUFORT, NORTH CAROLINA                                     to job-profit degradation of legacy projects and the pandemic.
                                                       MICHAEL DAVIS, PM&E BRANCH HEAD,
                                                       PWD JAX, NAVFAC SOUTHEAST          The greatest blow to direct job profits was Project P-464. Its booking
                                                                                          position was significantly underestimated in the 2021 reserve by $7.4 million.
         NAVFAC MID-ATLANTIC P-680 CH-53K
         CARGO LOADING TOWER                                                              Of this, approximately $5 million was for general conditions due to extended
         MARINE CORPS AIR STATION NEW                                                     time caused primarily by the poor performance of the mechanical design-
         RIVER, NORTH CAROLINA
                                                                                          build subcontractor. The project has exceeded the contract completion date
                                                                                          (CCD) date of July 16, 2021, and the government continues to issue additional
                                                                                          scope through RFPs beyond the CCD. Haskell is aggressively pursuing
                                                                                          submission of Requests for Equitable Adjustment (REAs) for the late RFPs
                                                                                          to offset $35,000/day liquidated damages and additional cost impacts of
                                                                                          unilateral modifications the government fails to recognize. Haskell has
                                                                                          submitted Time Impact Analysis (TIA) 3 for a time extension through
                                                                                          January 28, 2022, and is working on TIA 4, incorporating late government
                                                                                          RFPs for additional time. This project is in the final stages of commissioning
                                                                                          and punch list, with turnover scheduled in the first quarter of 2022.